| 1 | Installation, commissioning and dismantling of 1000mm wide x 490 mtr long, 90KW x 2, 550V belt conveyor in RVIIA seam from 46L/10ED to 46L/4WD for B1 panel of SHCM at Shyamsundarpur Colliery under Bankola Area.” |
| 2 | Transportation & installation of complete drive drum driven drum with gear motor base frame-12,5MT+discharge unit-2.5MT+tail end-1MT+Load table-1M+Hoop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-490mtr @106Kg/mtr =51.94MT +11 times Tail end extension-11MT= total weight =86.54 MT |
| 3 | Fitting of tail end and discharge scraper. |
| 4 | Belt laying including transporting of belt, jointing, tensioning. trial run etc |
| 5 | Foundation bolting for fitting of drive unit, discharge unit, loop take up & tail end etc =120nos |
| 6 | Cleaning of coal & unused materials before installation job |
| 7 | Making, and fabrication of Load table |
| 8 | Fencing of drive, loop take up & tail end |
| 9 | Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding. gas cutting etc. considering cost of consumables. |
| 10 | Dismantling of complete drive drum driven drum with gear motor base frame-12.5MT+discharge unit-2.5MT+tail end -1 MT+Load table-1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc-2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-490mtr @106Kg/mtr =51.94MT = total weight=75.54 MT |
| 11 | Taken out and coiling of belt |
| 12 | Cost of M.S. Nut bolts & washers |
| 13 | Cost of Belt fastener/joint E-35 Comb and grip type suitable for 13 Mato make machine available in mines |
| 14 | Drive base frame, Loop take up base & discharge base 14 cement concrete |
| 15 | Installation, commissioning and dismantling of 1000mm wide x 175mtr ong, 90kW, 550V belt conveyor in RVIIA seam from 43L/10ED to 43L/15ED for B3 panel of SHCM at Shyamsundarpur colliery under Bankola Area. |
| 16 | Transportation & installation of complete drive drum driven drum with gear motor base frame-12.5MT+discharge unit-2.5MT+tail end-1MT+Load table-1MT+loop take up with tension trolley drum-3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc -2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-170ntr @106Kg/mtr =18.55MT +3 times Tail end shifting(extension)-3MT=total weight=45.15 MT |
| 17 | Fitting of tail end and discharge scraper. |
| 18 | Belt laying including transporting of belt jointing tensiong trial run etc |
| 19 | Foundation bolting for fitting of drive unit, discharge unit, loop take up & tail end etc=120nos |
| 20 | Cleaning of coal & unused materials before installation job |
| 21 | Making, and fabrication of Load table |
| 22 | Fencing of drive, loop take up & tail end |
| 23 | Making vertical support from roof and floor for hanging the 8 conveyor structure from drive head to discharge by welding. gas cutting etc. considering cost of consumables. |
| 24 | Dismantling of complete drive drum driven drum with gear motor base frame-12.5MT discharge unit-2.5MT+tail end-1MT+Load table-1MT+loop take up with tension trolley drum- 3.60MT+Fix unit-1MT+motor, winch starter & switches cables etc-2.0MT+1000mm wide conveyor structure with top, bottom roller & foot stool-170mtr @106Kg/mtr=18.55MT = total weight -42.15 MT |
| 25 | Taken out and coiling of belt |
| 26 | Cost of M.S. Nut bolts & washers |
| 27 | Cost of Belt fastener/joint E-35 Comb and grip type suitable for Mato make machine available in mines |
| 28 | Drive base frame, Loop take up base & discharge base cement concrete |
| 29 | Installation and commissioning of 1200mm wide x 420mtr long long, 3.3kV HT belt conveyor in RVIIA seam from 11L/10D to 11L/22D for C2 panel of SHCM at Shyamsundarpur colliery under Bankola Area |
| 30 | Transportation & installation of complete 1200 mm double drive unit with gear motor& base frame -21MT + discharge unit -2.75 MT + loop take up with tension trolley drum-3.6MT +fixed unit with drum -1MT +load table 01 nos =1MT +tail end -1MT +1200 mm wide conveyor structure with top bottomroller & foot stool 420mtr x 80kg/mtr =33.6MT + starter and cable-1.5 MT+Tail end extension/shifting-10MT- total weight =75.45 MT |
| 31 | Making load table 01nos |
| 32 | Fitting of tail end and discharge scraper |
| 33 | Belt laying including transportation of belt jointing, tensioning trail run etc |
| 34 | Providing bolts and nut for fitting of above structure 420mtr 1.5Kg/mtr=630kg load table discharge & bend pulley loop take =630kq |
| 35 | Foundation bolting for drive unit 38 nos + discharge unit 24 nos + loop take with fixed unit 36 + tail end (4x11)-44nos total =142 nos |
| 36 | Making vertical support from roof and floor for hanging the conveyor structure from drive head to discharge by welding gas cutting etc considering cost of consumables |
| 37 | Cost of belt fasteners |
| 38 | Cleaning coal and unused materials & levelling the floor 9 before installation of drive unit base discharge unit base loop take up tail end |
| 39 | Fencing of drive & tail end etc |
| 40 | Drive base frame, discharge base & loop take up cement concrete |
| 41 | Installation and commissioning of 1200mm wide x 385mtr long long, 3.3kV HT belt conveyor in RVIIA seam from 6L/10D to 6L/21D for C3 panel of SHCM at Shyamsundarpur colliery under Bankola Area |
| 42 | Transportation & installation of complete 1200 mm double drive unit with gear motor& base frame -21MT + discharge unit -2.75 MT + loop take up with tension trolley drum-3.6MT + fixed unit with drum -1MT +load table 01 nos =1MT +tail end - 1MT +1200 mm wide conveyor structure with top bottom roller & foot stool 385mtr x 80kg/mtr = 30.8MT + starter and cable-1.5 MT+Tail end extension/shifting-9MT- total weight =71.65 MT |
| 43 | Making load table 01nos 1 Nos |
| 44 | Fitting of tail end and discharge scraper |
| 45 | Belt laying including transportation of belt jointing, tensioning trail run etc |
| 46 | Providing bolts and nut for fitting of above structure 385mtr 1.5Kg /mtr =570kg load table discharge & bend pulley loop take =570kg |
| 47 | Foundation bolting for drive unit 38 nos + discharge unit 24 nos loop take with fixed unit 36 + tail end (4x10)-40nos total =138 nos |
| 48 | Making vertical support from roof and floor for hanging the 7 conveyor structure from drive head to discharge by welding gas cutting etc considering cost of consumables |
| 49 | Cost of belt fasteners |
| 50 | Cleaning coal and unused materials & levelling the floor 9 before installation of drive unit base discharge unit base loop take up tail end |
| 51 | Fencing of drive & tail end etc |
| 52 | Drive base frame, discharge base & loop take up cement concrete |