| 1 | for Approch Road Construction of embankment with approved material obtained from borrow pits with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of table 300-2 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 2 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 3 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 4 | Providing and applying primer coat with SS grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 5 | Providing and applying tack coat with bitumen VG-10 using bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 6 | Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 7 | Providing and applying tack coat with bitumen VG-10 using bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 8 | Providing and laying bituminous concrete with higher capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 9 | Construction of Subgrade earthen shoulders with embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 10 | for Box Culvert Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 11 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 12 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 13 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 14 | RCC Grade M25 using batching plant transit mixer & Concrete pump (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 15 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 16 | RCC Grade M20 using batching plant transit mixer & manual placing (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 17 | Providing weep holes in brick masonry/ stone masonry plain/ reinforced concrete abutment, wing wall, return wall with 100mm dia AC pipe extending through the full width of the structure slope of 1(V) 20(H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204.3.7 As per SOR No-MORD 600/12.9 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 18 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 19 | Running of 5HP pump for dewatering including arrangement of pump suction and delivery pipes and other accessories at site including cost of POL As Per SOR NS (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 20 | For Protection Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with equirements of lines, grades and cross-section, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical specification Clause 302.3 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 21 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification as per Ref. to MORD Spec 305.3.9 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 22 | Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 23 | RCC Grade M25 using batching plant transit mixer & Concrete pump (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 24 | Providing weep holes in brick masonry/ stone masonry plain/ reinforced concrete abutment, wing wall, return wall with 100mm dia AC pipe extending through the full width of the structure slope of 1(V) 20(H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204.3.7 As per SOR No-MORD 600/12.9 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 25 | Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications Clause 1301 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 26 | for Road diversion Construction of embankment with approved material obtained from borrow pits with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of table 300-2 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 27 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 28 | Providing and laying 600mm dia NP-3 RCC hume pipe medium duty confirm to IS 458:2003 including collars/spigot jointed with stiff mixture of cement in the proportion of 1:2(1 cement :2 fine sand) including testing of joints all taxes transportation charge & contractor's profit etc. complete. Excluding all taxes (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) Please Enable Macros to View BoQ information |