| 1 | Earth work excavation and depositing on the bank with initial lead and lift of 10metres and initial lift in hard stiff clay stiff black coton hard red earthmurram, gravel stoney earth and earth mixed with small size boulders and hard gravelly soils (SS 20A) etc., complete as per std., specifications - |
| 2 | Plain cement concrete1:5:10 (One cement five sand and ten aggregate) using 40mm ISS HBG metal including cost of material, labour charges and all other incidental charges etc., complete as per std., Specification. |
| 3 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). |
| 4 | Providing and laying in position, standardised concrete Mix M-20 Grade using In-situ Concrete batching plant/ Ready Mix Concrete (RMC) adopting weigh batch method in accordance with IS 456 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 325 kg/m3 and maximum water cement ratio of 0.55, including admixture (plasticiser / super plasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete,improve workability without impairing strength and durability with about (5 Cu.m) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 Cu.m) 5156 kg. of 10- 12mm machine crushed stone jelly and with about (4.79 cu.m) 7670 kg. of crushed stone sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including Conveyance of concrete from batching plant to Work site, Electricity charges and other works & labour cost involved for concrete production, laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers. The coarse and fine aggregates to be used should comply with the requirements of IS standards. (No separate payment will be made by the Department for the excess usage of materials). In Foundation and Basement |
| 5 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steelreinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) |
| 6 | Supplying, fabricating, erecting structural steel work for roofing welded or bolted type using MS channels, angles, plates and round bars etc. conforming to IS specification including primer coating and enamal painting as per Design given by the departmental officers etc, complete as per standard specification |
| 7 | Supply, delivery and fixing of Highly pressed poly propyler sheet including cost of fabrication charges, fixing charges, including jointing bolts, nets and bitumen washers all cost of labour charges, handling charges etc., complete as per std., specification. |
| 8 | Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9\\"X43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification |
| 9 | Plastering with cement mortar (1:5), 12mm thick in all floors including cost and conveyance of all materials to site and labour charges etc, complete complying with standard specifications (S.I.309) |
| 10 | Supplying and filling in foundation, basement, etc with conveyed earth in layers of not more than 150mm thick layers well watered, rammed with surface vibrator and consolidated including conveyance charges etc. complete complying with standard specification and as directed by the departmental officers. |
| 11 | Painting two coats with ready mixed Plastic Emulsion Paint approved quality and colour over a priming coat, including thorough scrapping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required etc, complete as per standard specification. |
| 12 | Painting two coats with Ready Mixed Enamel Paint over the new iron works of approved quality and colour without priming coat including the cost all materials etc.,complete, in all floors. |
| 13 | Paving the floor with pre-polished concrete anti-skid tiles (Required shape and design) of 20mm thick of approved quality and colour laid in accordance with IS 1443 over a cement mortar bed of 20mm thick in Cement Mortar 1:3 (One Cement and Three crushed stone sand) with required Cement Slurry and Mortar Plasticizer and pointed with white cement mixed with colouring pigment at the rate of 0.40 Kg. / sq.m., curing, etc., complete complying with standard specification and as directed by the departmental officers. (The make and brand of the tiles should be got approved by Executive Engineer before use on works) |
| 14 | Manufacturing, Supplying and Fixing of Stainless Steel Hand rails for staircase using 50mm dia 304L Grade Stainless Steel pipe of 1.60mm thick at required locations to a height of 900mm from finished floor level welded to 38mm dia Stainless Steel pipe post of 1.00mm thick as vertical at 900mm centre with 2 Nos. of 25mm dia intermediate horizontal stainless steel pipe of 1.60mm thick in between. The vertical pipe has to be welded to the 100 X 100 X 6mm MS base plate encased in the base concrete. The rate is inclusive of the charges for cutting, bending, welding, grinding, polishing, conveyance, electrical charges, etc. complete Please Enable Macros to View BoQ information |