| 1 | NIT No.: Date: STANDARD BIDDING DOCUMENT FOR PROCUREMENT OF WORKS Rejuvenation of Water Body at Lal Dighi Pond, District Jalandhar Cantt, Punjab under AMRUT 2.0 Scheme Volume -3 Project Value: Capital Cost: Part-A & B Percentage Rate Rs. 229 Lakh O&M Cost Part-C Percentage Rate Rs. 22.38 Lakh. Price Bid June, 2025 NIT No.: Date: Name of Work:Rejuvenation of Water Body at Lal Dighi Pond, District Jalandhar Cantt, Punjab under AMRUT 2.0 Scheme Name of Bidder: General Summary S.No Particulars Total Amount (Rs) Capital Works: Percentage Rate |
| 2 | CIVIL (PART-A) |
| 3 | ELECTRICAL (PART-B) |
| 4 | 5 years' O& M (PART-C) Estimate Amount (Part A,B, and C ) (In Rs): 25137806.291898996 Percentage Above/Below/At Par Select 0.0 % Amount as per percentage quoted, Percentage Rate (Part A,B & C) (Amount in Rs) 0.0 Amount In Words No Rupees and No Paise Provisional Sum (Not part of bidding) Rs in Lakh = 3.9299999999999997 251.37806291898997 255.30806291898998 Provisional Sum S.no. Description Unit Qty Amt.(Rs.lakh) Provisional Sum |
| 5 | Contingencies = 5 % of Capital Cost |
| 6 | Electrical Connection Charges Total : Provisional Sum (Not part of bidding) 3.9299999999999997 CIVIL WORKS S.no. CSR Ref. Description Unit Qty Rate (Rs) Rate (Rs. In Words) Amount(Rs) Capital Works CSR Items ( Part - A)- CIVIL Sub Head-1:Development of Parks (a)Softscape work |
| 7 | 32.4 (a) |
| 8 | 32.4 (b) |
| 9 | 32.9 (a) |
| 10 | 32.13 |
| 11 | 32.18 32.22 Planting seasonal flower in beds |
| 12 | 32.13 |
| 13 | 32.14 |
| 14 | 32.51 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 15 | 1877559.08 100449.41078 1978008.49078 (b) Construction of Pathway and Parking |
| 16 | 24.6 ( c ) |
| 17 | 10.6(b) (ii) |
| 18 | 10.13 (ii) |
| 19 | 14.116 |
| 20 | 32.75 |
| 21 | 32.57 (a) 14.107 Sand filling under floor and in wells of bridge foundation including handling withing 100 metres |
| 22 | 32.55 Providing and fixing of white river (Stone) pebbles size of 2\\" to 2.50\\" dia in natural colour at site of work including loading, unloading and carriage |
| 23 | 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 24 | From Lohand Khad 106 km Bajri : |
| 25 | From Mirthal 97 km |
| 26 | From Mirthal 97 km |
| 27 | From Haryaal 129 km |
| 28 | Difference in Rates of materials |
| 29 | 2670632.7300000004 142878.85105500004 2813511.5810550004 ( c ) Construction of Kachha Pathway 5081311.581055 Earth work excavation(For ordinary path way) 6.2 Earth work excavation in ordinary soil,exclusive of compensation of earth of earth (a) Kassi work undressed involving an average horizontal throw upto 2 meters and average vertical lift upto .5 meter including breaking of cloda. |
| 30 | Brick edging of foot Path 32.54 Edging of paths/ beds with bricks/tiles laid dry,including required excavation, refilling, consolidating with hand and spreading surplus earth neatly within lead of 50 m. |
| 31 | Difference in Rates of materials |
| 32 | 35496.744000000006 1899.0758040000003 37395.819804000006 Sub Head-2 : Construction of Boundary wall |
| 33 | 10.6(b) (ii) |
| 34 | 10.27 |
| 35 | 15.59 |
| 36 | 10.13 (ii) |
| 37 | 9.1 Boundary Wall |
| 38 | 16.17 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 39 | From Lohand Khad 106 km Bajri : |
| 40 | From Mirthal 97 km |
| 41 | From Mirthal 97 km |
| 42 | From Haryaal 129 km |
| 43 | Difference in Rates of materials |
| 44 | 2606386.1100000003 139441.656885 2745827.7668850003 2745827.7668850003 Sub Head-3: Construction of Gazebo (05Nos) |
| 45 | 10.6(b) (ii) |
| 46 | 10.13 (ii) |
| 47 | 18.52 (a) |
| 48 | 13.27(iii) 13.27(iii) Providing and fixing ( PPGL) precoated painted galvalume sheet roofing (size, shape and pitch of corrugation as approved by Engineer-in-charge) The end rib shall have anti cappillary groove and return leg. The steel sheet must be having yield strength of 550 MPa ( Fy= 550 MPa) metallic coated with Zinc- Aluminium alloy ( i.e. 55% Al, 43.4%Zinc, 1.6% Si-Zincalume) AZ150 ( Min. 150 bm/mm2 total on both sides), pre painted with super Durable Polyster XRW quality paint includes inorganic infrared reflective pigment. The sheet confirms to general requirement of AS/NZS 2728 type 4/ IS 15965 class 3 durability and gloss value of 25% -40%. should be supplied in single length upto 12 metre or as desired by Engineer-in- charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required |
| 49 | 16.2 For Main Gate |
| 50 | 16.17 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 51 | From Lohand Khad 106 km Bajri : |
| 52 | From Mirthal 97 km |
| 53 | From Mirthal 97 km |
| 54 | From Haryaal 129 km |
| 55 | Difference in Rates of materials |
| 56 | 297926.65 15939.075775000001 313865.725775 Sub Head-6:Construction of Badminton Court (02 Nos) |
| 57 | 32.54 (a) |
| 58 | 6.2 (a) |
| 59 | 10.6(b) (ii) |
| 60 | 10.13 (ii) |
| 61 | 18.53 |
| 62 | 5.2 (i) 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 63 | From Lohand Khad 106 km Bajri : |
| 64 | From Mirthal 97 km |
| 65 | From Mirthal 97 km |
| 66 | From Haryaal 129 km |
| 67 | Difference in Rates of materials |
| 68 | 7848.940000000002 419.9182900000001 8268.858290000002 Sub Head-7:Providing and fixing Floating High & Heavy Cascade Fountain 14026.978290000003 |
| 69 | 10.6(b) (ii) |
| 70 | 10.13 (ii) |
| 71 | 14.87 |
| 72 | 14.72 For base of fountain |
| 73 | 14.89 (b) 5.2 (i) Earth,Surkhi,Sand,earth,Fly Ash,Bajri,Ballast,Stone Boulders,Kankar and Building Rubbish,Earth |
| 74 | From Lohand Khad 106 km Bajri : |
| 75 | From Mirthal 97 km |
| 76 | From Mirthal 97 km |
| 77 | From Haryaal 129 km |
| 78 | Difference in Rates of materials |
| 79 | 5167745.0 5428138.609999999 290405.415635 5718544.025634999 10886289.025635 Capital Works ' CSR based Civil Items ( In Rs) 12923988.863999998 Add 5.35% on CSR-Punjab-2022 items on account of change in GST rates for work contracts approved under Agenda item no.1 in the meeting of direction committee of Chief Engineers on dates 28-02-2023 and is issued vide memo No.2433-2452 /CSR dated 02-03-2023 0.0535 691433.4042239999 Total Capital Works Amount after adding 5.35% ( In Rs) 13615422.268223997 7990369.359999999 21605791.628223997 4625648.86 Capital Works Non CSR Items ( Part - A)- Civil Sub Head-1:Development of Parks (b) Construction of Pathway and Parking EPDM Rubber Florring |
| 80 | NS Sub Head-4:Sensory play Equipment for Specially Abled/Divyang Platform Merry Go round: |
| 81 | NS Out door Muzi Chime: |
| 82 | NS Musical Drum: |
| 83 | NS Sub Head-5:Playing and Gym Equipments |
| 84 | NS Sub Head-6:Construction of Badminton Court (02 Nos) Badminton net |
| 85 | NS Sub Head-7:Providing and fixing Floating High & Heavy Cascade Fountain High & Heavy Cascade Fountain |
| 86 | NS Capital Works ' Non CSR based Civil Items ( In Rs) 7990369.359999999 Capital Works ( Part - A) \\" Civil \\" CSR based amount after adding 5.35% ( In Rs) 13615422.268223997 Non - CSR based amount ( In Rs) 7990369.359999999 Total : Part - A ( CIVIL) CSR + Non CSR Amount : ( Rs) 21605791.628223997 Electrical Works, Lal Diggi Pond- Jalandhar Cantt. Sr.No. Item No. Description Unit Quantity Rate (Rs) Rate (Rs. In Words) Amount (Rs.) (Electrical Works) Supply, Installation, Testing and Commissioning of the following Items complete in all respect and as per Scope of Work, Specification and as required at site: 1. Capital Works ' CSR based Items B GI Pipe Pole & Cement Muff for Lighting Poles; 34.29 A GI PIPE POLES: Supply and erection of G.I. pipe ‘A’ quality of suitable length and dia. confirming to IS:1239 (Part-I) 1979, including fixing up to a given depth below G/L, the hole of excavation about 30cm dia. and given depth to be filled in up to 15cm below G/L with 1:2:4 cement concrete including painting of pole with two coats of approved aluminium paint as required:- |
| 87 | (i) 34.33 CEMENT CONCRETE MUFFS: (v) Making of cement concrete muff of overall size 450mmdia., suitable length (15cm below ground level) with 1:2:4 cement concrete mixture. The muff is to be made around the steel tubular pole/GI pipe pole. The outer surface of the muff shall be finished with 1:2 cement plaster with two coats of white snowcem complete in all respect as approved and desired by the Engineer in- Charge at site:- |
| 88 | (a) D Wiring, Lighting & Accessories, AC (for Panel Room): 34.03 RECESSED HDPE PIPE WIRING SYSTEM WITH MODULAR SWITCHES: Wiring in PVC insulated copper conductor single core FR cable (ISI marked), overall 1.5sq. mm, 1100volts grade to be laid in HDPE electrical conduit pipe 20mm/25mm dia. ISI Marked, recessed in wall etc., complete with powder coated/anodized concealed metal boxes (1.6mm thick with Brass lugs) required for suitable number of modules (Modular accessories) for having Step type electronic fan regulators (two module) 100watts, bell push, 6Amp. 2/3 universal socket (shuttered), 16/20Amp. combined/ universal Socket (shuttered), 6/10Amp. Switches, 16/20Amp. switches with indicator etc. and covered with Frame Plateetc., PVC connector (For Fan Box and Call Bell), PVC Bush, Steel Hooks, Sheet metal fan box (1.6mm thick shape hexagonal), CI Circular junction Boxes (Four way 1½\\" deep for walls and 3\\" deep for ceiling), bonding to earth with PVC insulated copper conductor single core FR cable (ISI marked) 1sq. mm, 1100volts grade (For 6Amp. wall socket & plug control point) and other petty material etc., including the cost of above material, cutting and filling up of chases (with finishing the surface):- |
| 89 | (i) a |
| 90 | (vi) 34.09 (xiii) Supply and erection of PVC insulated PVC sheathed (3 core) round flexible wire with copper conductor (FR) cable (ISI marked) confirm to IS:694/1990 left bare in pipe or casing of suitable size complete in all respect as desired by the Engineer-in-charge:- |
| 91 | (c.) 34.17 SHEET METAL DOUBLE DOOR DISTRIBUTION BOARD FOR MCB's/RCBO's/ RCCB's: Supply and erection of sheet metal double door Phase segregated distribution boards IP 43-IK09 metal door (dust protected) as per IS:8623-1&3, IEC 61439-1&3 suitable for flush mounting with fully insulated copper busbars, shrouded neutral bars, earth bars, cement spill protector, color-coded interconnecting wire set, cable ties, blanking plates and circuit identifications label and of required no. of ways for mounting miniature circuit breakers/ RCBO's/ RCCB's in the distribution board (For SP&N distribution board with rovision DP MCB's/ RCCB's/ RCBO's as incomer and SP MCB's as outgoings and for TP&N horizontal distribution board with provision TPN/ FP MCB's/ RCCB's/RCBO's as incomer and SP MCB's as outgoings) as per PWD General Specifications including connections with suitable size of thimbles and bonding to existing earth etc. |
| 92 | (i) 34.16 A MINIATURE CIRCUIT BREAKERS: Supply and erection of Miniature Circuit Breaker MCB's for circuit protection against overload and short circuit current fault suitable for 240/ 415 volts 50cycles AC supply with breaking capacity of 10KA, Curve-C and low watt losses as per IS/IEC 60898-1, energy limitation class-3, true contact indication, label holder facility in the existing MCB distribution board as per PWD General Specifications including connections with suitable size of thimbles/lugs:- |
| 93 | (vi) E Cable, Wire & Accessories; 34.10 D XLPE INSULATED UN-ARMOURED CABLES (LOOSE): Supply, laying and erection of aluminium conductor XLPE insulated PVC sheathedUn-armoured and served cable 1100 volts grade as per IS 7098 (Part-1)1988 tobe laid loose in the existing trench or pipe as per PWD General Specifications:- |
| 94 | (xxvi) 34.37 DOUBLE WALLED CORRUGATED (DWC) HDPE PIPES: 34.37 A Supply and erection of Double Walled Corrugated (DWC) HDPE pipe to be laid1mtr. below ground level including excavation placing the pipe in position and back filling with excavated soil etc. of the required size:- |
| 95 | (ii) 34.33 (vii) Supply and erection of SMC Junction Box (Glass Fibre reinforced polyester sheet moulding compound) confirm to IS:14772 (Recessed/ On surface), robustly constructed, safe & shock proof, rust & tamper proof of suitable inner & outer dimensions with ± 10% tolerance in size & hinged water tight cover with locking arrangement having 1No. terminal strip with 4Nos. terminals & 1No. Single pole MCB of required capacity fixed on din bar (Din Bar Provision for 2Nos. MCB's) complete in all respect as approved and desired by the Engineer In-Charge at site:- |
| 96 | (a) (xii) Supply and erection of PVC insulated PVC sheathed FR (2Core) round flexiblewire with copper conductor cable (ISI marked) confirm to IS:694/1990 left barein pipe or on surface with cleats of suitable size complete in all respect as desired by the Engineer-in-charge:- |
| 97 | (d) 34.38 C Supply and erection of heavy duty brass single compression gland for cable end termination duly complete with checknuts etc. including making necessary connections. |
| 98 | (iii) |
| 99 | (ix) 34.38 A Supply and erection of heavy duty aluminium thimbles/lugs for cable end termination duly crimped including making necessary connections completely:- |
| 100 | (vi) F Earthing for LT Panel, Feeder Pillar & Poles; 34.13 (xv) Earthing earth rod 20 mm dia for providing earth connections upto line earth with G.I. Wire 8 S.W.G. (4mm dia.). The rod shall be tapered at one end and flatted on other end. The hole size 10mm dia shall be drilled on the flatened side for facilitating connection with G.I. wire and thimble etc. The rod shall be erected in ground upto complete length vertically:- |
| 101 | 34.13 (xx) Capital Works 'CSR based Electrical Items' (In Rs) 547346.05 0.0535 29283.013675000002 Add 5.35% on CSR-Punjab-2022 items on account of change in GST rates for work contracts approved under Agenda item no.1 in the meeting of direction committee of Chief Engineers on dates 28-02-2023 and is issued vide memo No.2433-2452 /CSR dated 02-03-2023 Capital Works 'CSR based Electrical Items' after adding 5.35% (In Rs) 576629.0636750001 2.Capital Works ' Non-CSR based Items A LT Panel & Feeder Pillar; |
| 102 | NS C LED Post Top Lighting Fixture for Pole & Gate Lighting; (Ref: RUIDP ISOR 2023, 67.10) Providing & Fixing of IK08 IP65 protected Top/Bottom mounted LED Post top Luminarie made of single piece construction powder coated die cast alluminium housing with UV stabalized Clear / frosted Polycarbonate diffuser and Aluminium anodised with sand blast reflector. The System level Luminous efficacy ≥ 100 Lumen/W. SMD LEDs is to be used, System CRI>70, CCT: 3000/4000/6500 K. The integral electronic driver must be potted & has a unique BIS R number must be potted & has a unique BIS R number constant current and Internal/external surge protection device of min. 4KV(L- N) and efficiency > 85%, PF>0.9, THD<10% and input Voltage range of 140-270V AC at 50Hz. System life of 50000 Burning hours with 70% of Initial Lumens maintained . Driver current <750mA. Fixture must be in compliance with BIS Standards and Trade mark Certificate complete in all respect.OEM Must have its own in house NABL lab setup for all testing facilities for LED fixtures. (LM79/LM80) Certificate/ report with liable warranty of product/accessories from OEM shall be submitted. All as per pre approved by Engineer in-charge. For additional technical parameters of products/ work , refer Annexure \\"A\\" attached with this BSR . |
| 103 | D D Wiring, Lighting & Accessories, AC (for Panel Room): RUIDP ISOR 2023, 66.4 Providing & Fixing of IP20, 2'x2' LED Surface/ Recessed mounting Mid power SMD type LED Light fixture not less than 50mm housing depth made from CRCA sheet steel housing, high purity / transmisivity UV stabilized Non -yellowish diffuser for uniform light distribution. High efficiency with 4 KV internal/external surge protection BIS certified isolated driver having efficiency > 85% , with Short & Open circuit protection (Integral with light fixture). System lumen efficacy of ≥ 120 lm/Watt ,THD < 10 % , p.f.≥0.95,CRI >80 , life time of minimum 50000 Burning Hours with , 70% of intial Lumen maintaned till life ends , CCT 3000°K / 4000°K / 5700°K /6000°K/6500°K (As per ANSI Bin) , maximum power consumption should not more than the specified rating and Fixture shall be of BIS standard and trade mark certificate ( T.C.). Manufactures Word Mark/ Name Engraved/ Embossing/ Screen printing on housing.OEM must have its own in house NABL lab setup for all testing facilities for LED fixtures. (LM79 & LM80) certificate / Report from OEM shall be submitted. All as per pre approved by Engineer in- charge. All as per pre approved by Engineer in-charge. For additional technical parameters of products/ work , refer Annexure \\"A\\" attached with this BSR . Surface Mounting (Ref: 66.4.2) |
| 104 | RUIDP ISOR 2023, 64.12 RUIDP ISOR 2023, 64.12 Providing & Fixing of Heavy duty capacitor start, copper wound Double ball bearing 900/1400 RPM single phase Exhaust fan conforming to IS:2312 ISI marked in existing opening including making connections testing etc. as required. All as per pre approved by Engineer in-charge. For additional technical parameters of products/ work , refer Annexure \\"A\\" attached with this BSR . |
| 105 | Capital Works 'Non CSR based Electrical Items' (In Rs) 717577.0 Total : (Electrical) CSR + Non CSR Amount : (Rs) 1294206.063675 Operation & Maintenance S.no. CSR Ref. Description Unit Qty Rate (Rs) Rate (Rs. In Words) Amount(Rs) 5 Years' Operation & Maintenance Cost (PART-B) |
| 106 | NS 5 Years' Operation & Maintenance Cost ( Part - C) 2237808.5999999996 |