| 1 | Construction of embankment with approved material obtained from availble land as permitted and approved by Engineer-in-Charge and as per Technical Specitaion Clause 301.3.4.1, with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of Tables 300.1and 300.2 as per Technical Specification clause 301.5 Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 2 | Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting , trimming bottom and slopes, in accordance with requirements of lines, grades and cross sections within all lifts and lead . Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 3 | Providing ,Laying ,spreading Material on prepared sub grade ,adding cement @2% by weight to the spread material manually ,mixing in place with rotavator and compacting with the road roller at OMC to achive the desired unconfined compressive strength and to form a layer of sub-base. Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 4 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 5 | Providing ,Laying ,spreading Material on prepared sub grade ,adding cement @ 4% by weight to the spread material manually ,mixing in place with rotavator and compacting with the road roller at OMC to achive the desired unconfined compressive strength and to form a layer of base. Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 6 | Construction of Shoulder with approved material obtained from availble land as permitted and approved by Engineer-in-Charge and as per Technical Specitaion Clause 301.3.4.1, with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of Tables 300.1and 300.2 as per Technical Specification clause 301.5 Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 7 | Providing and applying tack coat with Bitumen V.G._10 using Bitumin pressure distributor at the rate of 0.35 kg per sqm on the prepared surface cleaned with hydraulic broom . Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 8 | Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates from approved quarry with using VG_10 @ 1.46 Kg per Sqm bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades. Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 9 | Providing and laying seal coat composed of 6.7 mm aggregates from approved quarry with using VG_10 @ 0.65 Kg per Sqm bitumen to required sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type 'C'. Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 10 | Earthwork in excavation for structures as per drawing & technical specification clause 305.1 including setting out, construction of shoring & backing, removal of stumps & other delecterious matter, dressing of sides & botton, backfilling the excavation the remaining earth locally for road work [as per MORD-302(i)SL 3.5] Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 11 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed aggregate 40 mm nominal size mechanically mixed,placed in foundation and compected by vibration including curing for 14 days. As per mord Spe-800 Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 12 | Granular material GSB filling in foundation trenches as per drawing & technical specition clause 305.3.9 on the sides of Hume pipe Ave Rate of 22.4-53,6.7 mm & Stone dust Including all material, labour & T&P with all taxes etc. complete but excluding GST |
| 13 | Providing,laying and fixing of reinforced concrete pipe 450 mm dia NP3 for culvert on first class bedding of granular material in single row with cement mortar1:2(1cement: 2 coarse sand) [as per MORD specification no. 9.3-1100(B)] Including all material, labour & T&P with all taxes etc. complete but excluding GST Please Enable Macros to View BoQ information |