| 1 | Providing, lowering, laying in trenches, aligning, fixing in position and jointing Ductile Iron (DI) ISI marked K-9 grade S&S pipes as per IS:8329-2000 (amended up to date), with internal cement mortar lining suitable for potable water with rubber ring (EPDM) joints as per IS: 5382-1985 including all taxes (Central and local), transportation and freight charges, inspection charges, loading/ unloading charges, including cost of labour and material, specials (Tee, bend etc.) satisfactory hydraulic testing, disinfection, commissioning etc. complete as per technical specifications and direction of Engineer-in-charge. (excluding earth work) Note : Providing and fixing of all requisite specials as per drawing, design and layout are inclusive in RM measurement of the item and shall not be paid separately. |
| 2 | 200 Dia DI K-7 Pipe line at various Village in |
| 3 | De-jointing and removing of already laid CI/DI pipes of following diameters in excavated trenches with care, without damaging pipes, CID joints, valves, specials etc. and other materials and then refilling of soil after de-laying and de-jointing of pipelines with proper compaction and disposing of all surplus soil as directed with in a lead of 30 mtr. This also include stacking the pipes with care and transporting the same to div./sub div. store or as directed by EIC with in the division. (Rates are Exclusive of Earth Work) |
| 4 | 200 mm Dia. DI Pipe |
| 5 | Laying, Jointing, Testing and Commissioning of Ductile Iron (DI) Pipes of any class in assorted length with specials, valves etc. including local handling and transportation from PHED store and then refilling of soil with proper compaction and disposing of all surplus soil as directed with in a lead of 30 mtr as per satisfaction of EIC. (Rates are Exclusive of Earth Work and jointing materials) |
| 6 | 200 mm Dia. DI Pipe |
| 7 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in trenches of required width and gradient for laying and jointing of pipe line including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 Mtr. including taking out the excavated soil, and then returning the soil as required in layers not exceeding 20cm in depth including consolidating each deposited layer by ramming, watering etc. and disposal of surplus excavated soil as directed within a lead of 50 Mtr. including required all safety provisions etc.:All kinds of soil |
| 8 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in trenches of required width and gradient for laying and jointing of pipe line including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 Mtr. including taking out the excavated soil, and then returning the soil as required in layers not exceeding 20cm in depth including consolidating each deposited layer by ramming, watering etc. and stacking serviceable material for measurements and disposal of unserviceable material as directed, with in a lead of 50 Mtr. including all safety provisions required .: |
| 9 | Ordinary rock |
| 10 | Hard rock |
| 11 | Dismantling of cement concrete pavement for pipe line line and chambers by mechanical means using pneumatic tools, cutting the peripheral edge by CC cutter, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 meters. Measurement for dismantled trench to be made as per standard trench width specified in tender document and no extra payment shall be made be made for trench width more than specified, re-handling of material/earth to complete the tasks as per technical specification and scope of work. |
| 12 | Providing and laying in position cement concrete M10 grade nominal mix 1:3:6 (1 Cement : 3coarse sand : 6 graded stone aggregate 40 mm nominal size) in base course complete including all material, labour, machinery, lighting, guarding for road restoration work in trenches of pipe line and chamber work. Measurement for CC work to be made as per standard trench width specified in tender document and no extra payment shall be made be made for trench width more than specified, complete work as per technical specification and scope of work. |
| 13 | Providing and fixing of flanged/ plain ended MS Specials made from MS sheet strips of relevant IS specification of approved thickness by welding, lowering, laying, aligning, fixing in position at all level/ depths in trenches complete including all taxes, material, labour, inside lining, outside coating, testing and commissioning along with pipe line as per technical specifications and direction of Engineer-in-charge. |
| 14 | MS pipe specials up to 600mm dia (with minimum 5mm thickness sheet) Please Enable Macros to View BoQ information |