| 1 | Execution of work |
| 2 | Earth work in excavation by manual means in foundation of boundary wall (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. (ordinary rock) |
| 3 | Providing and laying cement concrete 1:4:8 (1 cement: 4 coarse sand: 8 stone aggregate of 20 mm nominal size) in foundation of boundary wall including ramming compacting and curing etc complete. |
| 4 | Random rubble masonry with cement mortar 1:6 (1 cement: 6 coarse sand) in foundation and plinth of boundary wall including levelling up with cement concrete 1:6:12 (1 cement: 6 coarse sand: 12 graded stone aggregate 20 mm nominal size) upto plinth level etc complete. |
| 5 | Providing and laying in position specified grade of reinforced cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate 20 mm nominal size) in plinth of wall excluding the cost of cantering, shuttering, finishing and reinforcement etc complete. |
| 6 | Provision of Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Mild steel and Medium Tensile steel bars. |
| 7 | Provision of Form work of cantering and shuttering including strutting, propping etc and removal of form for roof height of 3 mtr height including labour and material etc complete for Plinth beam. |
| 8 | Provision of Coursed rubble masonry of boundary wall in cement mortar 1:6 (1 cement: 6 coarse sand) with hard stone (first sort) in superstructure above plinth level etc complete. |
| 9 | Supply and fixing of MS grill fencing on the boundary wall for safety and security of the site with MS angle 40x40x5mm vertical post and same size angle horizontal support of top middle and bottom for adjoining the frame 12 mm dia bar with arrow headed on top and placed vertically at a distance of 100 mm c/c and fixed together by nut bolt etc complete as per design/drawing attached. (Grill Panel size 2.00x1.50 mtr). |
| 10 | Provision for fixing M.S. Gate with two leaf with angle iron 40x40x5 mm, flat iron 40x5 mm and 12 mm dia bars with arrow headed on top and placed vertically at a distance of 100mm c/c fabricated as per design/drawing attached including all the supply of materials fabrication and fixing of the same. Required proper completion of work at the site. (Size 2.00 x 1.80 mtr) |
| 11 | Provision for Coping with 50 mm thick sand stone on top of wall with 20 mm. thick bed of mortar of ratio 1:6 cement and c sand . Coping stone to be laid with fine dressing and making side end as semi-circular shap (Bull nose type) etc complete including all the labour material and T&P required proper completion of work at the site. |
| 12 | Provision for fixing of M.S. grill for Safety & security of structure with angle iron 30x30x3 mm, flat iron 25x5 mm and 10 mm dia bars placed vertically at a distance of 8 cmm c/cfabricated as per designed by the department including all the supply of material, fabrication and fixing etc. ( Size 0.95 x 1.80 mtr) |
| 13 | Provision for fixing of M.S. grill for Safety & security of structure with angle iron 30x30x3 mm, flat iron 25x5mm and 10 mm dia bars placed vertically at a distance of 8 cmm c/c fabricated as per designed by the department including all the supply of material, labour and T. & P. required etc. (Size 0.65 x1.20 mtr) |
| 14 | Provision for fixing of M.S. door with door frame of angle iron 40x40x5 mm, door shutter with angle iron 30x30x3 mm flat iron 25x5 mm and 10 mm dia bars placed verically at a distance of 7.5 cm c/c fabricated as per designed by the department including all the supply of material, labour and T. & P. required at site. (Size 0.60 x 1.80 mtr) |
| 15 | Provision for Applying priming coat with ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel works. |
| 16 | Provision for Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade: Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture. |
| 17 | Provision for Flush pointing on stone work of boundary wall with cement mortar 1:3 (1 cement: 3 fine sand) including racking, cleaning and washing out joints etc complete. |
| 18 | Provision for removal of malba, heap of soil mixed with stone, plant chunks, vegetation growth and outer refused including excavation of malba, shorting of useful material (as RR stones for reuse in masonry work) collection with proper manner and disposal of refused out of 500 mtr from site by mechanical transportation including loading and unloading with all the labour material and T&P required proper completion of work at the site. |
| 19 | Provision for restoration/underpinning work of disturb , damaged, out of plumb , cracked brick work with old lakhauri/country brick with mortar of ratio 1:1:1 lime, surkhi and C.sand with mixing of Gur/sheera, Dry Gum, Dry belgiri etc. Including removing of damaged ruined masonry work, racking dead mortar, washing of surface, filling of joints and cracks etc. Its also including core treatment with filling of liquid lime mortar. Including all the supply of material labour and T&P. Required proper completion of work at the site. |
| 20 | Providing and laying of lime concrete under foundation and floor base with mortar of ratio 1:1:1:4 (1 lime : 1 Surkhi:1 Coarse sand : 4 Stone ballast 25 mm nominal gauge) with mixing of gur/sheera, dry gum, dry belgiri etc including mixing of concrete, laying, ramming beating and compacting etc. Including all the labour, supply of material and T&P. Required proper completion of work at the site. |
| 21 | Provision for 50mm nominal thickness lime plaster work for flooring work over lime concrete base with mortar of ratio 1:1:1 (1 lime : 1Surkhi: 1 coarse sand) with mixing of gur/sheera, dry gum, dry belgiri etc. Lime plaster flooring work will be laid by making expansion joints of thickness not more than 5mm as required. Including making proper levelling and gradient. Including all the labour, supply of material and T&P etc. Required proper completion of work at the site. |
| 22 | Provision for 20 to 30mm (25mm nominal thickness) lime plaster work in plain and simple molded with mortar of ratio 1:1:1 lime, surkhi, coarse sand with mixing of gur/ sheera, dry gum, dry belgiri etc. Plaster work to be executed in to coats as required after carefully removing of dead, decayed and salt effected lime plaster with carefully washing and cleaning surface. Including all the labour, supply of material and T & P Required proper completion of work at the site. |
| 23 | Provision for repair/restoration of richly carved molded lime plaster work with floral and geometrical design of thickness 20-30mm with mortar of ratio 1:1:1 lime, surkhi, coarse sand with mixing of gur/ sheera, dry gum, dry bilgir etc. Plaster work to be executed in to coats as required after carefully removing of dead, decayed and salt effected lime plaster with carefully washing and cleaning surface. Including all the labour, supply of material and T & P Required proper completion of work at the site. |
| 24 | Provision for repair of damaged sun shed/projection on wall as per original pattern with original used country bricks with lime mortar and lime plaster with 20 mm thick over sun shed with mortar both side of ratio 1:1:1 lime, surkhi and c. sand. with mixing of gur/sheera, dry gum, belgiri etc. Including all the supply of material, labour and T.&P. required proper completion of work at the site. (Lower sun shed (Projection - 30 cm) long wall side) |
| 25 | Provision for repair of brackets of sunshed made with country bricks and decorated/moulded lime plaster of thickness 10 - 12 mm of mortar of ratio 1:1:1 lime, surkhi and c.sand with mixing of gur/sheera and T.&P. Required proper completion of work at the site. |
| 26 | Provision for erection of scaffolding with scaffolding pipes, challies and other required articles for proper execution of work and removal of the same after work. Including all the labour, supply of material and T&P Required proper completion of work at the site. |
| 27 | Provision for earth work in filling in down area/low level area/under plinth of foundation trenches .Including necessary supply of soil (free from grass, garbage and other foreign material) from a distance not exceeding 8.00 km from site of work and including watering and compaction etc including all the labour, supply of material & T&P required proper completion of work at the site. |
| 28 | Provision for in environment development as grassing of ground with doob grass and show plants by levelling and ramming of ground with mixing of compost with soil. Including all the labour, material and T&P Required proper completion of work at the site. |
| 29 | Provision for making of masonry tank of size 2.50 x 1.50 x 0.90mt for slacking of lime, mixing grinding of lime mortar for conservation work. tank will be made by stone masonry, cement concrete etc. Including all the supply of material labour & T & P. Required proper completion of work at the site. |
| 30 | Provision for repair of damaged sunshed/projection on wall as per original pattern with original used country bricks with lime mortar and plaster with 20 mm thick lime mortar both side of ratio 1:1:1 lime, surkhi and coarse sand with mixing of gur/sheera, dry gum belgiri etc. Inculding all the supply of material, labour and T & P required proper completion (Upper sunshed projection 45 cm long wall side) Please Enable Macros to View BoQ information |