| 1 | (A)Dismantling 800 GPM pump motor set with Base plate, & 6\\" dia suction pipe 8 mtr. with foot valve. |
| 2 | Dismantling Non – return valve 1 no., sluice valve- 1 no and Both side matching Reducer 8\\" X 6\\" sluice valve 2 Nos. Pump body Match piece 8\\" X 6\\" - 2 Nos. 6\\" dia bend 8 Nos.& short piece pipe 4 Nos. from 800 GPM 6” dia delivery line. (18 Nos. X 2 time = 36 Nos.) |
| 3 | Manual Shifting all above dismantle 1 No. pump motor set, bands, short piece pipes and kept at safe place for joining. |
| 4 | Dismantling 6” dia 40 Nos. (240 Mtr.)pipe in Vertical / incline position.Manually lower down & carrying all above dismantle pipe from vertical /incline position. |
| 5 | Loading 6\\" dia 40 Nos.(240Mtr) pipe on truck & unloading at joining site |
| 6 | Manual carrying , laying & joining of 6” dia 40 Nos. pipes (240 Mtr) in incline position |
| 7 | Carrying, laying & joining 6” dia bend 6 Nos., And tapper short piece pipe 4 Nos. Sluice valve-1, Non- returning valve-1, & pump body match piece 2no, Both side matching Reducer 2 Nos. for NRV. & S.V., & short piece pipe 4 Nos. & bend -2 Nos (22 Nos X 2 time = 44 Nos.) |
| 8 | Re-Installation 800 GPM pump motor set a new place Matching of suction 6” dia pipe . delivery range, priming and starting of pump. |
| 9 | Making 6” dia. Short piece pipe 6 Nos. & both side flange welding. |
| 10 | Making 6” dia bend 6 Nos. and both side flange welding. |
| 11 | Supply of 6” dia flanges for , short pipe & bands |
| 12 | Supply of Nut-Bolt |
| 13 | Supply of Oxygen Gas |
| 14 | Supply of DA Gas |
| 15 | Supply of Welding Rod |
| 16 | Repairing of 6\\" dia 1 No. Foot valve |
| 17 | Remodification of one No. base plate |
| 18 | Transporting of Oxygen , DA & Welding Machine etc |
| 19 | (B) Dismantling 6” dia 30 Nos. (180 Mtr.)pipe at NT quarry. |
| 20 | Loading all above dismantle 6\\" dia 30 Nos. pipe (180 mtr) from B-Patch and new pipe 6” dia 20 Nos. (120 Mtr.) pipe on truck from 6 No. incline & unloading at Joining site Jeenagora. joining site |
| 21 | Manually Laying 6”dia 20 Nos. pipes for flange welding & removing after welding at 6 No NT. Colliery for loading on truck & Flenge welding of 20X2=40 nos Flange. |
| 22 | Manually Carrying, Laying & joining of 50 Pipe ( 300 Mtr) i.e East Bararee 140 Mtr. & Jeenagora Coal depot -160 Mtr. including surface leveling & Supporting wherever required. |
| 23 | Repairing of 6\\" dia 10 Nos. old & damaged pipe. |
| 24 | Earth cutting work for dismantling and Joining . size:- 2(50 M X 0.609M X 0.457 M) = 27.83m3 |
| 25 | Carrying, laying & joining 6” dia bend 6 Nos., And tapper short piece pipe 8 Nos. for Both side. |
| 26 | Making 6” dia bend 6 Nos. and both side flange welding. |
| 27 | Making 6” dia. Short piece pipe 8 Nos. & both side flange welding. |
| 28 | Supply of 6” dia flanges for New pipe, short pipe & bands |
| 29 | Supply of Nut-Bolt |
| 30 | Supply of Oxygen Gas |
| 31 | Welding M/C Rant |
| 32 | Supply of DA Gas |
| 33 | Supply of Welding Rod |
| 34 | Transporting of Oxygen & DA |
| 35 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |