| 1 | Charges for conducting Geophysical Survey to locate for favourable point for drilling 6 ½\\" dia borewell |
| 2 | Providing 6\\" dia borewell in hard rock area including all accessories etc., complete as per standard specifications. |
| 3 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 4 | Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 5 | Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9\\"X43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 6 | Supply and Fixing Pipes and Specials etc.., |
| 7 | 2\\" Pvc pipe |
| 8 | 2\\" Pvc coupling |
| 9 | 2\\" Pvc Elbow |
| 10 | 2\\" Pvc tee |
| 11 | 2\\" Pvc bend |
| 12 | 2\\" Pvc Ball Valve |
| 13 | 50 mm HDPE Hose |
| 14 | Supply and run of 4.0 sq.mm PVC INSULATED AND SHEATHED 3 CORE FLAT TYPE COPPER CABLE The above cable should be adopted for Bore well submersiblepumpsets only |
| 15 | Supply of THREE PHASE SUBMERSIBLE PUMPSET SUITABLE FOR 150 MMDIA BOREWELL of lpm against head as per ISI foot valve arrangements with 30 mm G.I.Pipe 6m with 2 M.S. Union and all accessories etc.,complete as per standard specifications. 50x40 |
| 16 | Supply and delivery of direct online starter confirming to IS13947, IEC60947-1 and as amended thereafter with suitable KW rating for operation in AC/Three Phase/50HZ(± 5%) and 415 V(±10%) including Ammeter, Voltmeter, Thermal Overload relay, 16 Amps 2 pole Magnetic Contactor with under Voltage protection, Indication lamp, starting capacitor, running capacitor and On/Off Push button switches, 5 way connector, wiring with 1 sq. mm/1.5 sq. mm copper PVC insulated cable, powder coated vermin proof box including the capacitor (the cost of capacitor is to be taken separately). 3 HP |
| 17 | Labour charges for the erection of submersible pumpset in borewell/openwell including fixing and jointing submersible cable with proper clamps upto the starter to required depth and also fixing of riser pipes to the required depth valves erection clamps, pressure gauges upto the exterior wall of pump room and erection of panel board consisting of TPICN switches starter, Voltmeter, Ammeter, three pilot (indicating) lamps capacitor single phasing preventor, water level guard and laying and jointing the cables and twin earthing as per IE rules etc., complete and testing the pumpset and trail run for 10 days. |
| 18 | Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications |
| 19 | Earth work Excavation for laying of 63mm Pvc Pipes as directed by departmental officers complete as per standard specification. |
| 20 | Lowering of 63mm pvc Pipes as per gradient as directed by departmental officers Complete as per standard Specification. |
| 21 | Refilling the Excavated trenches after lawing of 63mm pvc Pipe Complete as per standard Specification Please Enable Macros to View BoQ information |