| 1 | Repair to potholes any depth, not exceeding 1 sqm each including sweeping free from dust and mud, or water, scoring sunken surfaces in roads, paths, etc., cutting around edges to at least 25 mm in depth, making good by applying tack coat with VG-10 at the rate of 5 kg per 10 sqm, putting in semi dense bituminous concrete consolidated/ compacted thickness using hot mix plant and mechanical paver using graded crushed stone aggregate premixed with binder (paving grade bitumen VG-30 grade) @ 5.5% by weight of total mix & hydraulic lime filler, rolled and compacted to required camber and gradient complete all as specified and as directed. Note :- (i) Semi dense bituminous concrete shall be laid using self propelled hydrostatic paver finisher and preparation of mix shall be using hot mix plant and transporting the mix in tipper.(ii) The exact bitumen content required shall be determined following the Marshall Mix Design procedure contained in the Asphalt Institute Manual MS-2 (Sixth Edition) as referred in case 3.5.3 of IRC 111: 2009. (iii) The minus adjustment in rate due to variation in quantity of bitumen on lower side if any shall be priced at the rate of ₹44 per kg. No adjustment shall be made for bitumen more the 5.5%. |
| 2 | Scarifying or picking gravelled, macadam or bituminous macadam surfaces in area exc 400 sqm and depth not exc 50mm and removing exc 50m complete all as speified and directed |
| 3 | M&L 150mm thick WBM (compacted thickness) laid in two layer .consolidate thickness of each layer is 7.5cm of WBM, with granite/basalt coarse aggregates of grading 2 (63 to 40mm size) or of grading 3 (50 to 20mm size), spread,rolled and consolidated and rolled to 8 to 10 ton power roller to required gradient and camber . |
| 4 | M&L Preparing unsurfaces water bound macadum surface by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surface with gunny bagsand air compressor to remove all loose dirt etc. complete all as specified and as directed. |
| 5 | M&L Preparing black top surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surface with gunny bagsand air compressor to remove all loose dirt etc. complete all as specified and as directed. |
| 6 | M & L for applying evenly a tack coat with of bitumen VG-10 grade confirming to IS:73 with cationic bitumen emulsion RS-1 grade at the rate of 10 Kgs per 10 Sqm on existing bituminous, cement concrete or primed granular surface to ensure a bond between the surface being paved and the overlaying course using mechanical sprayer complete all as specified and as directed by Engr-in-Charge |
| 7 | M&L premix bitumen macadam with binder content 4% of bitumen (paving bitumen VG -30 grade) by the weight of total mix laid, rolled and compacted to required gradient and camber (consolidated thickness75 mm or less ) with 8 to 10 tonne power roller complete all as specified and directed. |
| 8 | M&L for applying evenly a tack coat with of bitumen VG-10 grade confirming to IS:73 with cationic bitumen emulsion RS-1 grade at the rate of 3 kgs per 10 Sqm on existing bituminous, cement concrete or primed granular surface to ensure a bond between the surface being paved and the overlaying course using mechanical sprayer complete all as specified and as directed by Engr-in-Charge |
| 9 | M&L for applying evenly a tack coat with of bitumen VG-10 grade confirming to IS:73 with cationic bitumen emulsion RS-1 grade at the rate of 5 Kgs per 10 Sqm on existing bituminous, cement concrete or primed granular surface to ensure a bond between the surface being paved and the overlaying course using mechanical sprayer complete all as specified and as directed by Engr-in-Charge |
| 10 | M&L for 30 mm thick (consolidated thickness) bitumenous premixed semi dense asphaltic concrete carpet with 5.5% binder content paving bitumen VG-30 by weight of total mix and stone dust using as filler material, laid with mechanical paver, rolled and compacted with 8 to 12 tonne power roller to required camber and gradient.Note:-(i) Premix concrete shall be mixed in hot plant, transported from plant to work site and laid/ spread by means of mechanical paver.(ii) Filler for semi dense asphaltic concrete shall be cement, lime and stone dust @ 2% of total weight of binder.(iii) The exact bitumen content required shall be determined following the Marshall Mix Design procedure contained in the Asphalt Institute Manual MS-2 (Sixth Edition) as referred in case 3.5.3 of IRC 111: 2009. (iii) The minus adjustment in rate due to variation in quantity of bitumen on lower side if any shall be priced at the rate of ₹44 per kg. No adjustment shall be made for bitumen more the 5.5%. |
| 11 | M&L for preparation of new /old surfaces providing and making lines, dashes , arrows, letters etc on road applied hot thermoplastic road marking paint with glass beads min 2.00 mm thick complete in all respects such as furnishing all labour, material, tool, Equipment incl all incidental cost necessary to carryout the work at site conforming to technical specification clause no.803 of MORT & H specifications 4th Revision of 2001/Latest edition complete all as specified and directed. |
| 12 | General Notes1.Only batch mix plant shall be used in the work.2. The Contractor shall, prior to procurement and commencement of bituminous work, submit a valid Memorandum of Understanding (MoU) with the proposed hot mix plant for approval of the Garrison Engineer (GE). The contractor shall arrange a visit of GE/Engineer-in-Charge to the plant for inspection prior to approval of the MoU. It shall be ensured that the bituminous mix is procured only from an approved Batch Mix Plant, and no material shall be procured or laid without such prior approval.3. Rolling shall be carried out to achieve a field density of not less than 98% of the Marshall bulk density of the approved Job Mix Formula.4. The contractor shall ensure that all bituminous mix brought to site is weighed at an approved Government Weighbridge or a weighbridge duly approved by the Engineer-in-Charge. Each load shall be supported with authentic weighment slips indicating gross weight, tare weight, and net weight. 5. The contractor shall submit the original weighment slips, duly defaced and certified by the Engineer-in-Charge, along with each Running Account Receipt (RAR) bill for processing of payment. No payment for bituminous work shall be considered unless supported by such authenticated original weighment slips. Please Enable Macros to View BoQ information |
| 13 | General Notes1.Only batch mix plant shall be used in the work.2. The Contractor shall, prior to procurement and commencement of bituminous work, submit a valid Memorandum of Understanding (MoU) with the proposed hot mix plant for approval of the Garrison Engineer (GE). The contractor shall arrange a visit of GE/Engineer-in-Charge to the plant for inspection prior to approval of the MoU. It shall be ensured that the bituminous mix is procured only from an approved Batch Mix Plant, and no material shall be procured or laid without such prior approval.3. Rolling shall be carried out to achieve a field density of not less than 98% of the Marshall bulk density of the approved Job Mix Formula.4. The contractor shall ensure that all bituminous mix brought to site is weighed at an approved Government Weighbridge or a weighbridge duly approved by the Engineer-in-Charge. Each load shall be supported with authentic weighment slips indicating gross weight, tare weight, and net weight. 5. The contractor shall submit the original weighment slips, duly defaced and certified by the Engineer-in-Charge, along with each Running Account Receipt (RAR) bill for processing of payment. No payment for bituminous work shall be considered unless supported by such authenticated original weighment slips. Please Enable Macros to View BoQ information |