| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. - All kinds of soil |
| 2 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete. |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level: 1:3:6 ( 1 Cement: 3 fine sand : 6 graded well burnt brick aggregate 20 mm nominal size) |
| 4 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement -All work upto plinth level: 1:1½:3 ( 1 Cement: 1½ fine sand : 3 graded stoneaggregate 20 mm nominal size) |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills,staircases and spiral stair cases upto floor five level excluding the cost of centring, shuttering, finishing and reinforcement 1:1½:3 ( 1 Cement: 1½ fine sand : 3 graded stone aggregate 20 mm nominal size) |
| 6 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo-Mechanically Treated bars of grade Fe-500D ormore |
| 7 | First class brick work in foundation and plinth including cost of all materials as required complete:- In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 8 | Half brick masonry work with second class bricks in superstructure upto floor five level including cost of all materials as required complete:-In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 9 | 12 mm cement plaster of mix12.1.1 Cement mortar 1:4 (1 cement : 4 fine sand) |
| 10 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering --All work upto plinth level:1:2:4 ( 1 Cement: 2 fine sand : 4 graded stone aggregate20 mm nominal size) |
| 11 | Centering shuttering including struttings, propping etc. and removal of form work for: Suspended floors, roofs, landings, balconies and access platform with timber planks Please Enable Macros to View BoQ information |