| 1 | Cutting uprooting and clearing jungles including shrubs, water weeds, bushes, trees, plants, upto 30 cm. girth including removing as directed by Engineer-in-charge. |
| 2 | Supplying Jhaw / Eucalyptus bullah piles at work site, including dressing and making one end pointed. Note: Diameter of pile to be measured at a distance of 1.5m from the thicker end.15.00 cm av. Diameter |
| 3 | Labour for driving Jhaw / Eucalyptus bullah piles by monkey in all sorts of soil including hoisting and placing piles in position, protecting the pile head with iron ring and cutting and shaping heads before and after driving and including hire and labour for necessary driving appliances and all tackles. 15.00 cm av. Diameter |
| 4 | Supplying, fitting and fixing with iron nails half split bullah wailing pieces and cross pieces etc.complete with cost of all materials and carriage to site.Width of thinner end above 15cm (i) Jhaw / Eucalyptus |
| 5 | Coal tarring with 5% pitch including cost of material and labour complete as per direction of the Engineer-in-charge.Two coat. |
| 6 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur variety. |
| 7 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation, basement and upto roof of ground floor/upto 4 m Tor steel/Mild Steel II JSN/JSPL/SHYAM/SRMB/BMASL/ELECTROSTEEL/SSL |
| 8 | Supplying at site High Density Polyethylene (HDPE) bag of size 0.84 m x 0.38 m conforming to BIS : 14252 : 2015 for bank protective works including all cost of cost of transportation on road by all means,including other incidental charges complete. |
| 9 | Labour charges for filling HDPE bags with filler materials (earth/sand), machine stitching the open end of the bag with thread as per design and placing the same on slope or dumping from bank within initial lead of 30m and all lifts including carriage and hire charges of all materials and equipments but excluding the cost of filler materials as directed by Engineer-in-Charge (Volume of earth/sand filled bag should not be less than 0.0328 cum). |
| 10 | Earthwork in excavation in all kinds of soil for making embankments, repairs to the embankment, closing breaches etc. as per profile including supply and transporting the earth by truck or tractor or any other mechanical means on land , including loading, transporting, unloading and stacking with all lifts bothways and head load where necessary and depositing the same on embankments, clannels, filling depressions in requisite profile, levelling as per direction of the Engineer-in-charge within a lead of, NB :- Measurement to be taken on the basis of stack measurement / prepost work section measurement after deduction of void as per norms. No extra payment will be made for stacking |
| 11 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) 25 mm to 30 mm shuttering without staging in foundation. |
| 12 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing,s preading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. Depth of excavation not exceeding 1,500 mm. Please Enable Macros to View BoQ information |