| 1 | Part A-Chain link fencing compound wall and concrete flooring |
| 2 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-incharge: 1:3:6 or richer mix (i/c equivalent design mix) all complete. |
| 3 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : |
| 4 | P/L, of dry stone soling duly hand packed for foundation and backfilling with ramming, dressing, and compacting all inclusive leads, lifts, loading, un-loading, cost and carriage of material involved complete. |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) all complete |
| 7 | providing and supplying iron slag, to be used in cement concrete path 1:2:4 equipment, complete in all respects as per specifications and directions of the engineer in charge. |
| 8 | Providing and fixing in position Stainless steel Grade 304 plate-1.0 mm thick as per design for expansion joints. 200 mm wide |
| 9 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form work for: Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc complete. |
| 11 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns etc complete. |
| 12 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 13 | Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-incharge. Made of G.I. wire of dia 4 mm all complete. |
| 14 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade.Two or more coats on new work (Steel work). |
| 15 | Carriage of materials :- Sand 20mm for an average lead of 14Kms. |
| 16 | Carriage of materials :-Stone agg 20mm for an average lead of 10Kms. |
| 17 | Carriage of materials :-Stone agg 40mm for an average lead of 10Kms. |
| 18 | Part B-Good earth filling including grassing |
| 19 | Supply and filling of good earth ( suitable for turf) from approved source upto site of work including ramming dressing and watering in 15/22cm layers including spreading levelling and consolidation with power road roller of 8 to 10 tone capacity (to required gradient and camber with all leads and lifts carriages for an aveg lead of 11 kms, head load T&P establishment charges etc complete.(finished work to be measured) |
| 20 | Grassing with selection no. 1 grass including watering & maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds & fit for mowing including supplying of good earth if needed (the good earth shall be paid separately.) with grass turf all complete. |
| 21 | Part C-Wooden Gazeebos 2 No.'s |
| 22 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : |
| 23 | P/L, of dry stone soling duly hand packed for foundation and backfilling with ramming, dressing, and compacting all inclusive leads, lifts, loading, un-loading, cost and carriage of material involved complete. |
| 24 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)all complete. |
| 25 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) complete. |
| 26 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. |
| 27 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete 50 mm thick with 20mm nominal size stone aggregate all complete. |
| 28 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all Welded complete. |
| 29 | Providing/Fixing of CGI Colour coated (Hi-Rib) profile sheets for roofing including vertical/curved surface fixed with Polymer coated J or l hooks, bolts and nuts 8mm diameter with bitumen and G.I Limpet washers or with G.I Limpet washers filled with white lead, including overlapping of sheets complete (upto any pitch in horizantal/ vertical or curved surface) excluding the cost of purlins, rafters (0.50mm thick) etc incl ridges hips/ valleys 60cm vide of colour GI sheets sheets including cost of screws/ washers all complete and cost and carraiges of materials complete. |
| 30 | Providing wood work in frames of false ceiling.partitionong etc.sawn and fixed in position (Budloo wood) |
| 31 | providing and fixing 12mm thick ply of apprved brand and manufacture in ceiling including nails, screws and other necessary fittings carriage complete as per the directions of EIC. |
| 32 | Flooring with marble stone of specified thickness as per sample of marble approved by Engineer-in-charge, over 20 mm (average) thick base of cement mortar 1:4 (1 cement:4 coarse sand) laid and jointed with grey cement slurry including rubbing, polishing and curing complete -Makrana White Second quality-16mm |
| 33 | providing and fixing in position wooden balusters of approved quality and design, including fixing with nails and shall be of second cladd deodar wood- all complete job and design and brand to be approved by EIC (@ 2ft spacing in each length of gazeebo) |
| 34 | Providing and fixing of decorated type garden bench of approved brand manufacture including all necessary fittings/fixtures complete design and pattern to be approved by engineer incharge. ( Payment shall be made as per actual measurement.) 3 seater-(45\\"x15\\"x20\\") |
| 35 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade Two or more coats on new work all complete. |
| 36 | filling and supplying GSB under floors in trenches, plinth sides of foundations etc.consolidating each deposited layer by ramming, dressing, and compacting all inclusive leads, lifts, loading, un-loading, cost and carriage of material involved complete. |
| 37 | Carriage of materials from approved source to site of work:- sand for an average lead of 14 Kms MT. |
| 38 | Carriage of materials from approved source to site of work:- Stone Agg for an average lead of 10 Kms MT. Please Enable Macros to View BoQ information |