| 1 | Opening of jumpers of 20 MVA 132/33 KV Transformer from CB,CT,LA, Isolator etc of HV & LV side |
| 2 | Dismantaling of 33 KV VCB from structure after opening of all cable connection Earthing all both side Jumpers and their structure and shifting of VCB from site to Store/Designated place as per supervising engineer. |
| 3 | Dismantling of old 3 No.36 KV CTs including opening of all cable connection jumpers & earthing etc and shifting to store |
| 4 | Dismantling of 30 KV LA (3nos) with structure |
| 5 | Dismantling of 132 KV LA (3 NO) with structure including opening of all cable connection Earthing & jumper and all other accessories necessary for shifting of main tank. |
| 6 | Draining of Transformer oil from 20 MVA T/F to oil drums. |
| 7 | Complete dismantling of 132/33 KV, 20 MVA Transformer accessories after opening of jumpers, removal of earthing and opening of cables and cable connection, removal of all radiators, conservator tank, oil pipe lines, all bushings, turrets, fan motors, marshalling box, RTCC etc. All other associated work to complete the jobs satisfactorily including proper stacking. Including providing blanking plates, nuts and bolts and gaskets as per required. All other T&P etc. Shall be arranged by the contractor as his own cost. |
| 8 | Dismantling of RTCC Panel of 20MVA Transformer |
| 9 | Shifting of main tank of 132 KV, 20MVA transformer main tank from plinth upto 20mtr distance including turning of Tank if required all T&P and all other works required to complete the job satisfactory at 132 KV S/S, Gangiri including all transformer accessories |
| 10 | Additional shifting of main tank of 20 MVA Transformer to safe distance. 5mtrs or part there of. |
| 11 | Shifting of main tank of new 132 /33 KV 63 MVA T/F from unloading point to plinth at 132 KV S/S, Gangiri upto 20mtr including turning of tank, if required, including cost of all required labour and special T&P along with all other works required to complete the job |
| 12 | Additional shifting of main tank of 63 MVA Transformer to safe distance. 5mtrs or part there of. |
| 13 | Complete erection of new 132/33KV, 63 MVA Transformer by erection of radiators conservator tanks, all bushing turrets connecting oil pipe lines, cooling fans, marshalling box, motor drive mechanism of tap changer, RTCC Panel etc.and all other accessories work to complete the job satisfactorily.Job including first filling of oil and topping up of transformer oil (not circulaion) in radiators oil pipe lines,conservator tank etc and all other associated work for completion of 132/33KV, 63MVA Power Transformer and accdessories provided by UPPTCL. |
| 14 | Installation of New RTCC panel of 63 MVA Transformer in Control room after making cable schedule ferruling properly, Ferrules provided by Contractor at his own cost. |
| 15 | Transformer 63 MVA TestingSFRA TestCapacitance & tan Delta Test of Bushing and WindingInsulation Resistance MeasurementCore InsulationMagmnetising CurrentShort Circuit TestMagnetic BalanceVector Group TestTurns Ratio Testwinnding resistance measurement |
| 16 | Centrifuging of complete transformer oil in transformer main tank by connecting centrifuging machine, to be arranged by the contractor along with operator and taking the B.D.V and PPM values of the oil periodically till the required value is achieved as per direction of supervising engineer at 132 KV S/S, Gangiri ( B.D.V. and PPM tester shall be arrange by contractor) |
| 17 | Earthing of New 63MVA Power Transformer HV and LV Neutral, Body ,Marshalling Box Drive Mechanism etc with 75*10mm ms flat including bending, cutting drilling and welding etc. |
| 18 | Checking and strengthening of Delta earthing for Transformer neutrals by additional welding and interconnections using 75x10 mm (MS Flat will be provided by UPPTCL) |
| 19 | Laying of following unarmoured cable as per specification & cable schedule. |
| 20 | 2cx2.5 Sq.mm |
| 21 | 4cx2.5 Sq.mm |
| 22 | 6cx2.5 Sq.mm |
| 23 | 10cx2.5 Sq.mm |
| 24 | Termination of control cable in the cable trench from control relay panel to marshling box,CT Junction box of T/F as per cable schedule and Schedule hand over to Supervising Engineer |
| 25 | Erection of New 33KV, 2000A, VCB including shifting of this VCB fro store/designated place to site, erection of structure, earthing of struture and lower side of pole termination work with proper indication local/remote operation and relay opertaion minimum three operation done of each local/remote close and trip local/remote. |
| 26 | Erection of New 33 KV Bus Isolator work by placing new 2000/1650A Bus Isolator channel,fixing operating mechanis and Earthing all channel and Mechanism box after taking minimum 05 freehand Ioslator operation found satisfatorily then rejumpering work by Twin Zebra/Moose |
| 27 | Erection of New 3 Nos 33 KV 2000/12501A CT work includes eathing of new CT and termination of all CT with CT junction box. |
| 28 | Erection of new 33kv CT Junction Box |
| 29 | Erection of new 30 KV LA (3 nos surge arrester) with structure and its earthing properly as per direction of supervising engineer. |
| 30 | Erection of 132 KV LA (3 NO) with structure including opening of all cable connection Earthing & jumper and all other accessories necessary for shifting of main tank. |
| 31 | Jumpering work of 132 KV new 63 MVA transformer, all 33 KV and 132 KV equipment and jack bus. |
| 32 | Transformer Oil sample collection, testing of transformer oil at CPRI/ERDA/Other lab Noida/Bhiwadi & finishing test report for a-Dissolve Gas Analysis test-01 Nosb-Breakdown Voltage Test-01 Nos.C-water content test-01 Nos. |
| 33 | Providing & fixing new generation energy saving & environment friendly long life versatile pressure die-cast aluminum outdoor high beam flood light with power 150 W LED as light source & exclusively designed polycarbonate cover along with electronic driver complete fitting suitable for 220 Volt AC input supply of IS make of CGL/ Havells /Surya/ Philips/ Bajaj etc. brand and providing & fixing of junction box (Size 150x150x200m) having of 01 No. 6Amp. Single pole MCB (L&T, Havells/Schneider make) . |
| 34 | Installation of 110 V DC Disribution Board By Proper connection with another DCDB and 110V Battery set and Proper foundation work and earthing. |
| 35 | Providing and fixing of Retro Reflective sign board of size 3feetx2feet |
| 36 | Supply portion :- |
| 37 | 33 KV Post Insulator clamp for Twin moose conductor made of al alloy LM-6 complete. |
| 38 | 4 Bolted Type PG Clamp suitable for Moose to Moose conductor complete with HDG nut bolt & washer as per technical specification. |
| 39 | Bimetallic 33 KV Isolator clamp for ASCR Twin Moose conductor complete for 2000/1250A with hot dip galvanized nut, bolts and washer as per technical specification. |
| 40 | 33 KV CT clamp suitable for ACSR Twin Moose conductor complete with hot dip galvanized nut, bolts and washer as per technical specification. |
| 41 | Supply of Portable Earthing Discharge rod of First class insulation for system voltage upto 400 KV having total height as 7200mm (24¨) one ste consisting 6.5 mtr long in four pieces made of epoxy bonded glass fibre, earthing cable with transparent PVC insulated 12mm² dia flexible copper wire fitted with line end earthing clamp of all alloy suitable 4\\"IPS tube and Canvas carry Bag. |
| 42 | Supply of tinned copper bond size 15x550mm long made of 12 mm multi strand rope type 450 mm long should be joined together and cramped with copper lug (20mm hole) on both ends as per sample. Please Enable Macros to View BoQ information |