| 1 | Demolition of cement concrete in flooring in 1:2:4 ( 1 cement : 2 sand :4 aggregate) including disposal of the waste material complete in all respect as per entire satisfaction of Engineer in Charge. |
| 2 | Demolition of old 15mm thick plaster in cm 1:6 ( 1 cement : 6 sand ) including disposal of the waste material within all leads and lifts complete in all respect as per entire satisfaction of Engineer in Charge. |
| 3 | Demolition of old 6 mm thick plaster in ceiling cm 1:3 ( 1 cement : 3 sand ) including disposal of the waste material within all leads and lifts complete in all respect as per entire satisfaction of Engineer in Charge. |
| 4 | Cement concrete in flooring in 1:2:4 ( 1cement : 2 Sand : 4 aggregate ) complete in all respect as per entire satisfaction of Engineer in charge. |
| 5 | 15mm thick plaster in C.M 1:3 ( 1 cement :3 sand ) including disposal of the waste material with in all leads and lifts comnplete in all respect as per entire satisfaction of Engineer in charge. |
| 6 | 6 mm thick plaster in ceiling in C.M 1:4 ( 1 cement :4 sand ) including disposal of the waste material with in all leads and lifts comnplete in all respect as per entire satisfaction of Engineer in charge. |
| 7 | Providing and fixing wood paneled glazed shutters for doors windows and clear story 40mm thick windows incluidng bright finished black enameled iron with necessary screws with second class deodar wood 40mm thick. |
| 8 | White washing with lime on undercoated wall surface ( two coats ) to give an even shade including thoroughly brooming the surface to remove all dirt dust and other foreign matter. |
| 9 | Finishing wall with water proofing cement paint of approved brand & manufacture 7 of required shade on undecorated wall surface ( two coats ) to give an even shade after thotoughly brushing the surface to remove all dirt & remains of loose powdered materials . |
| 10 | Painting two coats ( excluding priming coat) on new wood and wood based surface with ready mixed paint brushing the give and even shade incluidng cleaning of all dirt dust and other foreign matter and sand papering and stopping with ready mixed paint other than white. |
| 11 | Painting two coats ( excluding priming coat) on new steel and other metal surface with enemal paint brushing into give an even shade including cleaning of all dirt dust and other foreign matter and enamel paint other than white . |
| 12 | Removal of slips /silt/sand in all kind of soils ( incluiding saturated soils but excluding the boulders and rocky portion requiring blasting up to a distance of 20 mtrs Disposing off unserviceable materials stacking serviceable materials and neatly dressing the surface incluidng deployment of generator and raw water pump for removal of water from the percolation well gallery in order to remove the deposited materials complete in all respects within all leads and lifts as per direction and satisfaction of Engineer in Charge . |
| 13 | Providing form work with steel plates 3.15mm thick welded with angle iron frame 30 x30 x 5mm so as to give a fair finish incluidng centring shuttering strutting and propping etc with wooden battens and ballies height of propping and centering below supporting floor to ceilling not exceeding 4 meters and removal of the same for insitu reinforced concrete and plain . |
| 14 | Providing and laying cement concrete work 1 :2 :4 ( 1 cement : 2 sand : 4 graded stone aggregate 40mm nominal size) and curing complete excluding the cost of form work and reinforcement for reinforced concrete work in. |
| 15 | Cleaning of all type of concrete / masonary surface by throughly brooming with wire brush & surface grinder to remove the plaster algae dust dirt and all foreingn material consolidated on surface complete in all respect. |
| 16 | Water proofing treatment on water tank on specified or marked area where heavy leakages are noticed such as bottom of tank and horizontal joints of RCC pannels of walls including cost of cutting holes in the concrete with chieseling hammering and fixing nozzles for injection grouting of water proof compound of requted and brand such as perma Grout or equivalent make at one foot interval to block voids or cappilaries to arrest complete leakages of RCC water retaining structures as per direction and satisfaction engineer in charge . |
| 17 | Providing and laying water proofing treatment on inner wall surface of RCC water storage tank by applying cement slurry mixed with polymer water proofing compound of approved brand such as perma Hypercrete or equivalent make in ratio 1:1 or as recommended by the company including cost of providing fibre mesh in first layer ( over lap of joint of fabric mesh shall not be less then 10cm final layer of well stirred slurry of cement polymeric water proofing compound such as perma Hypercrete or equivalent make applied with brush in perpendicular direction complete with cost of cement and sand as per direction and satisfaction engineer in charge. Please Enable Macros to View BoQ information |