| 1 | Construction of Girls Toilet P U M School in Nedumbuli Panchayat |
| 2 | Earth work excavation for foundation in all classes of soils and sub soil to full depth except in hard rock requiring blasting but inclusive of shoring strutting if required for the sides of foundation. |
| 3 | Cement Concrete 1:4:8 mix using 40 mm HBG metal for foundaion including watering wherever necessary and laid in layers of not more than 15cm thick. Compacting etc., |
| 4 | Brock jelly 40mm size forFilling soak pit inner etc |
| 5 | Brick work in CM 1:5 mix using country bricks ground moulded of size 23 x 11 x 7 Cm for the following including curing etc., complete complying with standard specifications. |
| 6 | Supplying and Erection centering for sides and soffiots including necessaary supports and strutting as directed by the departmental officers Lintels, Staircase waist slabs, Landing slabs, Landing beam, Portico beam etc.) |
| 7 | Column upto Basement |
| 8 | Roof Projection side |
| 9 | Supplying and Fabricating and placing in position MS Steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and blinding wire all floors etc., complete complying with standard specification. |
| 10 | Rainforcement Cement Concrete 1:1 1/2:3 using 20 mm ISS HBG metal for all RCC item of works excluding cost of reinforcement and fabricating charges, centering and shuttering but icluding curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls, sides and bottom of the slabs, beams, etc., shall be finished smooth with cement mortar 1:3, 12mm thick and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications. |
| 11 | Paving the Top of roof with Solar reflective ceramic tiles of size 305 x 305 x 7mm thick of approved quality and colour laid in Cement mortar 1:3 (One cement and three M.Sand) 12mm thick and pointed with tile grout (Nitotile Grout or equivalent) and cement in the ratio of 1:3 for joint, curing etc., complete complying with standard specification and as directed by the departmental officers. (The make and brand of the tiles should be got approved by the Executive Engineer before use on works) |
| 12 | Supplying and fixing Polycarbonate 6mm thick and steel tubular box section of 100x50x3mm of 1meter interval including priming coat fixing in position with all necessary accessories complete complying with standard specification and as directed by the departmental officers. |
| 13 | Supplying, fabricating and erecting Structural steel works |
| 14 | Paving the floor with pre-polished concrete anti-skid tiles (Required shape and design) of 20mm thick of approved quality and colour laid in Cement Mortar 1:3 (One Cement and Three crushed stone M.Sand) 20mm thick and pointed with white cement mixed with colouring pigment at the rate of 0.40 Kg. / sq.m., curing, etc., complete complying with standard specification and as directed by the departmental officers. (The make and brand of the tiles should be got approved by Executive Engineer before use on works) Using anti-skid tiles (Observed Data) |
| 15 | Dadooing of walls with glazed tiles of size 15 cm x15cmx6mm laid in CM 1:2, 10mm thick & pointing with white cement using 0.4kg/cm2 including cost and conveyance of all materials and labour charges , etc, complete. |
| 16 | Plastering with CM 1:5, 12mm thick over the cement concrete for floor finish including curing etc., complete complying with standard specifications and as directed by the departmental officers. |
| 17 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work. |
| 18 | Manufacturing, Supplying and Fixing of Stainless Steel Hand rails for staircase using 50mm dia 304L Grade Stainless Steel pipe of 1.60mm thick at required locationsto a height of 900mm from finished floor level welded to 38mm dia Stainless Steel pipe post of 1.00mm thick as vertical at 900mm centre with 2 Nos. of 25mm diaintermediate horizontal stainless steel pipe of 1.60mm thick in between. The vertical pipe has to be welded to the 100 X 100 X 6mm MS base plate encased in the baseconcrete. The rate is inclusive of the charges for cutting, bending, welding, grinding, polishing, conveyance, electrical charges, etc. complete |
| 19 | Cost and Supply of steel doors and windows of Specified Gauge and thicness as Directed by the departmental offcers, including all labour charges and fabrication charges etc, complete. |
| 20 | Steel door 1.00m X 2.10m |
| 21 | PVC door 0.75m X 2.10m |
| 22 | RCC Jolly |
| 23 | Cost and Supply of Warter Closet,PVC Pipe Including all cost and convenyance for etc complete |
| 24 | Water Closet Indian types |
| 25 | Wash Basin |
| 26 | 2000 litre HDPE Tank |
| 27 | RCC Ring with Cover Slab |
| 28 | Provision for Sanitary Arrangements |
| 29 | Provision for Water Supply Arrangements |
| 30 | Provision for Door Fixing Charges |
| 31 | Painting Two coat approved Plastic Emulsion over the plastered surface including cost and all other charges etc., |
| 32 | Painting TWO coats of new iron works such as steel doors, windows,ventilators, window bars, balustrades etc., |
| 33 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \\"BB\\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) Please Enable Macros to View BoQ information |