| 1 | Formation |
| 2 | 3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m <br> Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 |
| 3 | OD456902/2025-2026:DRY RUBBLE MASONRY Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site. |
| 4 | 75.8.1.1:Providing plain/reinforced concrete(1 cement:2 fine aggregate: 4 course aggregate) forsubstructure as per drawings and technical specifications Clause 802, 803, 1202 & 1203as required including compaction, finishing and tamping etc .complete. Max. size ofcourse aggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
| 5 | 14.1:Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications Clause 1301 |
| 6 | OD468481/2025-2026:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 <br> I. P.C.C grade M 10 <br> (i) Nominal mix 1:3:6 (Derived from spec 11.4.1.1) |
| 7 | 11.4.2.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 II. P.C.C grade M 15 (i) Nominal mix (1:2.5:5) |
| 8 | 12.5.3:Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 For height upto 5 m III. R.C.C grade M 20 |
| 9 | 12.7:Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 |
| 10 | 3.3:Construction of Embankment with Material Obtained from Roadway Cutting <br> Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 |
| 11 | 3.14:Construction of Subgrade and Earthen Shoulders<br> Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. |
| 12 | OD463995/2025-2026:Supplying and fitting name board of size 75cm x 45cm made with GI plain sheets 1.25mm thickn (class IIII) fitted with 35 x 35x 4mm MS angle 2 Nos horizontally and 3 nos vertically to make a frame for strengthening the GI sheet fitted 2 Nos 32mm GI pipe vertically 90cm above from ground level and fixing in cement concrete 1:2:4 30cm x 30cm 30cm including cost and conveyance of all materials all labour charges fabricating etc complete. Please Enable Macros to View BoQ information |