| 1 | 934 - Mounting and connecting HT XLPE UG cable ends of all sizes upto and including 3x300 sq mm with special type cable clamps, bolts, nuts, terminal protectors etc.including cost of extra materials if needed and giving necessary jumper connections. |
| 2 | C-202425-6127-2 - Doing horizontal directional drilling along/ across roads, supplying and pulling 125mm HDPE pipe duct for drawing 11kV 3x300Sq mm Aluminium XLPE UG cable through the duct including surveying the site for collecting information about under ground utility installations and other obstructions using suitable modern sensing equipments, restoring the damages occurred if any, pit marking, pilot drilling, pre raming, closing of pits with normal soil/filled sand/crusher sand and consolidation to the satisfaction of the road owner and traffic police as they insist, taking the cable to the open trenches, RMUs, transformer yards etc., mounting the cable after providing loop at 1.2m depth , putting HDPE (PN-6,Kg/sq mm) at rising point(0.5 m below ground level and 1.5m above ground level) making RCC jointing chambers for straight joints if any, testing commissioning, placing route markers at 100m interval, writing identification name ,date of laying ,date of commissioning etc. legibly on the cable rising using polyurathane paint etc. as per the direction of departmental officers including supply of HDPE pipe. (includes cost of HDPE pipe, labour, transportation charges etc.) |
| 3 | 926 - Excavation of cable trench of appropriate size ( normally 1.2m deep and 0.35m /0.5m wide for single/double run) in all classes of soil including breaking clods, watering, ramming and sectioning of soil bank etc. and back filling the soil after cable laying and consolidating the soil in layers of 75cm (excluding laying of cable). |
| 4 | 163 - Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 5 | 157 - Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 6 | 161 - Additional rate for excavation of one Earth Pit (2.5m depth) in Hard Laterite. |
| 7 | 553 - Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 8 | 204 - Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. |
| 9 | 205 - Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 10 | 206 - Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 11 | 706 - Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 12 | 726 - Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 13 | 1109 - Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 14 | 1110 - Erection of suspension clamp for LT ABC of any size |
| 15 | 1114 - Providing Cable Tie |
| 16 | 1134 - Providing End Caps |
| 17 | 1141 - Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 18 | 119 - Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 19 | 132 - Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 20 | 151 - Installing one DTR Meter with box (normal size 40x25x100cm) on existing poles including fixing of 3 CTs on bus bar, laying and termination of control cable using proper lugs, fixing of meters, capacitors, control fuses and giving the complete connections including conveyance of materials. |
| 21 | 156 - Fitting one additional Fuse unit and giving connection from Transformer to fuse and Distribution box to LT OH line. |
| 22 | C-202425-6703-2 - Dismantling one set (3No.) 11kV DO Fuse from existing DP structure |
| 23 | C-202425-6703-1 - Dismantling one set (3No.) 11kV LA from existing DP structure |
| 24 | 517 - Dismantling (without damage) one AB switch from existing structure and bringing back to section store. |
| 25 | 568 - Dismantling one section fuse from structure and bringing back to section store. |
| 26 | 520 - Dismantling transformer station with transformer erected in DP structure by dismantling HT Double Pole Structure using PSC pole after disconnecting stay wires, 10 channel cross arms,AB switch, DO fuse, LA, GI earthing leads, DTR meter with box with metering equipments, CTs, Distribution Box, statutory display boards etc. but excluding the rate of dismantling transformer, earthing, stay sets & fencing. |
| 27 | 128 - Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 28 | 171 - Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 29 | 4.68 - Providing additional jumper from AB to line |
| 30 | 115 - Additional rate for providing one disc set, PG clamp etc. complete, on any type of HT pole for making cut point. |
| 31 | 405 - Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 32 | 952 - Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 33 | 167 - Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 34 | 951 - Constructing Transformer plinth of size 1.5x1.5x1.5m on 1.8x1.8x0.75m basement inclusive of cost of all materials. [Excavation 1.8x1.8x0.75m, Random Rubble in CM(1:6) 1.8x1.8x0.75m + 1.5x1.5x1.5m, concrete (1:2:4, 20mm) 1.5x1.5x0.10 m, plaster CM (1:3) 12mm, 1.5x1.5m, Pointing CM (1:3) 1.5x1.5mx 4 sides]. |
| 35 | 170 - Fitting one Additional 75x40mm,1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 36 | 1.88 - Additional rate for excavation of one Pit for Coil Earthing in Hard Laterite. |
| 37 | 703 - Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 38 | 513 - Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 39 | 354 - Dismantling existing 250kVA Transformer, erecting new 250kVA Transformer in place, giving connections etc. including loading/unloading of old and new Transformer at site. |
| 40 | 117 - Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 41 | 1002 - Transporting UG Cable |
| 42 | 931 - Doing straight joint on HT XLPE UG cables of sizes beyond 3x185 sqmm and upto and including 3x300 sq mm using the cable jointing kit supplied departmentally as per specification after providing proper traffic signalling and caution board fencing etc. wherever necessary, including charges for cable jointer and other sundries etc. as per the direction of departmental officers at site. |
| 43 | 1116 - Installation of Insulation piercing connector for main to service line main:16-95 sqmm, Tap : 4-35 sqmm |
| 44 | 1119 - Installation of Insulation piercing connector for main to service line main:16-95 sqmm, Tap 16-95 sqmm |
| 45 | 1132 - Fitting of one No. pole top service connection box of standard size (up to 4 way) using ss strap/B&N of suitable size in to the PSC/A poles at the standard height excluding giving connections |
| 46 | 565 - Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 47 | 610 - Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 48 | 209 - Additional rate for excavation of one Pit for LT Pole/LT Stay in Hard Laterite. |
| 49 | 1105 - Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 50 | 221 - Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 51 | 140 - Fitting 3 channel cross arms, AB switch, DO fuse, LA(Ord), HT & LT connections upto OH lines, etc. on existing DP structure, fixing distribution box/provision for one set (3No.) of LT fuses, drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing & mounting of Transformer on plinth. |
| 52 | 566 - Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 53 | 558 - Dismantling one damaged LT PSC/RCC Strut pole including removal of clamps and stacking. |
| 54 | 503 - Dismantling one damaged 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. Please Enable Macros to View BoQ information |