| 1 | Jogging Track |
| 2 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 3 | OD359956/2025-2026:Engaging labour for petty works |
| 4 | OD365258/2025-2026:Cleaning the surface and removing dirt,dust ,greese,oil,algae,fungus,vegetable growth etc. including washing the surface with the help of required scrubbers,and cleaniing with machine operated water jet etc. without causing any damages to the existing structures,fittings and fixtures etc. complete : |
| 5 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 6 | 11.20.2:Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand).Medium shade pigment using 50% white cement 50 % Grey cement |
| 7 | 16.47.1:Painting runway/ taxi track /apron making with adequate nos of coats to give uniform finish with road marking paint of superior make as approved by the Engineer-in-Charge, i/c cleaning the surface of all dirt, scales, oil grease and other foreign material etc. and lining out complete.New work ( Two or more coats) |
| 8 | Construction of additional two rows for amphitheatre |
| 9 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 10 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 11 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 12 | 50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge |
| 13 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 14 | 11.20.2:Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand).Medium shade pigment using 50% white cement 50 % Grey cement |
| 15 | 8.2.2.2:Providing and fixing 18 mm thick gang saw cut, mirror, polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations, of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 ( 1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels.Area of slab over 0.50 sqm |
| 16 | 8.3.2:Providing edge moulding to 18 mm thick marble stone counters, vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer -in-Charge.Granite work |
| 17 | Multipurpose lounge area |
| 18 | 15.23.1:Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.For thickness of tiles 10 mm to 25 mm |
| 19 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 20 | OD359909/2025-2026:Engaging labour for petty works |
| 21 | 16.78.2:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25 |
| 22 | OD359326/2025-2026:Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of stone aggregate of size 6mm, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. |
| 23 | OD359343/2025-2026:Supplying and fixing White Granite Stone outdoor benches of approve quality and make having size of 180x45x45cm or nearest available size including conveyance to the site ,fixing at different locations as directed by the departmental engineers in charge |
| 24 | Construction of kids play area |
| 25 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete |
| 26 | 50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. |
| 27 | 16.78.2:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25 |
| 28 | OD359912/2025-2026:Engaging labour for dismantling and refixing the SS handrails in the restoration area |
| 29 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 30 | OD356413/2025-2026:Supply and installation of 6mm thick EPDM + 30mm SBR system over Concrete sub base. 1) Primer with PU Binder over sub base. 2) 30mm thick Black SBR Granules mix with PU Binder as per the manufacturer's instructions. 3) 6mm thick Ecolastic EPDM 1-4mm Granules size mix with P U Binderas per the manufacturer's instructions. |
| 31 | OD359591/2025-2026:Supply and fixing Play equipment Double arch swing with Product zone 3.20mx1.10m & Play zone - 4.20m x 5.00m with following specifications:Legs of the swing are made of80NB B class GI CHS, Cross bar of the swing is made of 50NB B class GI CHS, Swing clamps are madeof PPCP(Poly propylene Co Polymer) Plastic, Stainless steel hook and bearing is provided in the clampfor the smooth functioning, Rubber dipped molded chains are used in the swing in order to prevent itfrom rusting as well as finger entrapment, Belt seat of the swing is made of 10mm thick rubber material.All metal parts are painted up to min 90 microns. All fasteners used in the assembly are made of stainlesssteel materials.(Concrete for fixing is to be paid separately) |
| 32 | OD359597/2025-2026:Supply and fixing Play equipment 3 feet straight slide with Product zone - 2.60mx0.60m & Play zone - 4.60m x 2.60m with following specifications:Slide made of Fibre reinforcedPlastic (FRP), 5mm wall thickness, Ladder steps made off 2mm thick GI sheets, Ladder handrails aremade of 15NB,20NB & 25NB B class CHS, Platform of the slide is made of 3mm thick GI sheets, Pillar ofthe platform is made of 80NB B class GI hollow section, end stay pipes are made of 20NB B class GICHS, All metal parts are painted up to min 90 microns. All fasteners used in the assembly are made ofstainless steel materials.(Concrete for fixing is to be paid separately) |
| 33 | OD359598/2025-2026:Supply and fixing Play equipment S Rail Scrambler with Product zone 4.30mx 2.40m & Play zone 5.30m x 3.40m with following specifications: Legs of the scrambler are madeof 50NB B class GI CHS and Railings of the scrambler are made of 25NB & 20 NB B class GI CHS. Allmetal parts are painted up to min 90 microns. All fasteners used in the assembly are made of stainlesssteel :Supply and fixing Play equipment S Rail Scrambler with Product zone 4.30m x2.40m & Playzone 5.30m x 3.40m with following specifications: Legs of the scrambler are made of 50NB B classGI CHS and Railings of the scrambler are made of 25NB & 20 NB B class GI CHS. All metalparts arepainted up to min 90 microns. All fasteners used in the assembly are made of stainless steel: Supply andfixing Play equipment S Rail Scrambler with Product zone 4.30m x 2.40m & Play zone 5.30m x 3.40mwith following specifications: Legs of the scrambler are made of 50NB B class GI CHS and Railingsof the scrambler are made of 25NB & 20 NB B class GI CHS. All metal parts are painted up to min 90microns. All fasteners used in the assembly are made of stainless steel materials. (Concrete for fixing is to be paid separately) |
| 34 | 16.68:Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. |
| 35 | Construction of Skating Area |
| 36 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete |
| 37 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 38 | OD359945/2025-2026:Engaging labour for dismantling and refixing the SS handrails in the restoration area |
| 39 | 16.4:Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road/ vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening / binding material to fill up interstices of coarse aggregate, watering and compacting to the required density. |
| 40 | 4.1.2:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3graded stone aggregate 20 mm nominal size derived from natural sources) |
| 41 | OD360279/2025-2026:Providing and laying vacuum dewatered flooring using M20 grade concrete 1:1.5:3 (1 cement:1.5 coarse aggregate:3 graded stone aggregate 20 mm nominal size) including vibrating concrete by using screed vibrator and vacuum dewatering using approved make equipment and finishing the top surface to required level and grade using power trowels of standard make.Rate include surface hardner ,covering the finished concrete surface and curing(based on CPWD 16.75&5.1.2) |
| 42 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 43 | OD360287/2025-2026:Providing installation of Polypropylene modular tiles of available standard colors for multisport of MVCmake as per below specifications:ITF certified, Double layered, Total thickness of 15.7mm, weight g /piece = 340, length 304.8mm & width 304.8mm, tile structure material – modified propylene polymerconnection inter-lock, warranty 5 years (including material, required side profile kerbs, line marking,transportation & labour excluding unloading at site, crew accommodation) Please Enable Macros to View BoQ information |