| 1 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 2 | Excavation in foundation in ordinary soil foul requiring the use of special T&P such as pickaxe, subbles etc. (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. (Excluding Royalty)( S.I. No.251) |
| 3 | Earth work in cutting or embankment in ordinary soil to be in 20 cm layers, including ,watering ,Dressing ,compacting ,ramming the soil to achive 95% proctor density ,and dressing the surface to be required levels and slope and also including 1.50m lift and 30 m lead . The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30m distance as directed by the Engineer-in-charge. (Excluding Royalty) |
| 4 | Providing and layingConcrete with 4cm gauge brick ballast, fine sand of 1.25 fineness modulous and cement in prportion of 1:6:12 in foundation in under floor , including supply of all material labour and T&P etc rfequired of proper completetion of the work . |
| 5 | RCC 1:1.50:3 with cement c'sand stone grit of 20 mm gauge in Slabs excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. |
| 6 | Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as directed by E/I. |
| 7 | Providing and fixing stainless steel (Grade channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners |
| 8 | Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and prepolished) machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations of required size of approved shade, colour and texture laid over 20mm thick base cement mortar 1:4 (1 cement: 4 coarse sand) with joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing moulding and polishing to edge to give high gloss finish etc. complete at all levels. Area of slab over 0.50 sqm |
| 9 | Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete. |
| 10 | Finishing wall with Acrylic smooth exterior paint of required shade new work ( two or more coat applied @1.67ltr./10 sqm over and including priming coat of exterior primer applied @2.20 kg/10 sqm ) as per D.S.R.No. 13.46.1 Please Enable Macros to View BoQ information |