| 1 | Safe Carriage of following material from Electricty store center Hts to Pit site of work through the Kacha and Pakka road including loading and unloading at the respective ends including the cost of arrangement of labour, T&P, etc. which required for proper completion of work.(Distance 00-50 Kms.) |
| 2 | Pcc Pole 8.5/9 Mtr. Long |
| 3 | STP Pole 9/11/13 Mtr. Long |
| 4 | Teeoff Channel with N&B |
| 5 | Earthing set complete |
| 6 | V type X arm |
| 7 | Pin Insulator with Pin |
| 8 | Disc Insulator with fitting |
| 9 | LT XLPE/PVC Cable |
| 10 | AB Cable |
| 11 | ACSR Dog Conductor |
| 12 | ACSR Weasel Conductor |
| 13 | XLPE Cable |
| 14 | Cable Jointing Kit |
| 15 | M/s Angle |
| 16 | MS Dropper Channel |
| 17 | Ms Top Channel |
| 18 | Stay set Complete |
| 19 | 100 KVA 11/0.4 KV T/F |
| 20 | Distribution Box |
| 21 | F Bracket |
| 22 | Fuse Set |
| 23 | Errection of following Poles with grouting including Cutting of kharanja/mettalic road/concrete portion while digging pit & complete H.T./L.T. fittings as per RESPO manual and as per direction of Engineer Incharge including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 24 | Pcc Pole 8.5/9 Mtr. Long |
| 25 | STP Pole 9/11/13 Mtr. Long |
| 26 | Fixing/ Errection of following item, cost of labor, material and T&P which required for completion of work |
| 27 | Teeoff Channel with N&B |
| 28 | Pin Insulator with Pin |
| 29 | Disc Insulator with fitting |
| 30 | V type X arm |
| 31 | MS Dropper Channel |
| 32 | Ms Top Channel |
| 33 | Ms Angle |
| 34 | Fuse Set |
| 35 | Cable Jointing Kit |
| 36 | Distribution Box |
| 37 | F Bracket |
| 38 | Installation of 100 kva T/F in proper alignment direction & making HT/LT connection. |
| 39 | Errection and grouting of stays as per RESPO Norms and as per direction of supervising engineer. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
| 40 | Fixing of earthing rod as per RESPO Norms and as per direction of supervising engineer. |
| 41 | Laying, sagging and stringing and jumpering/binding etc. in 33 KV/11 KV / LT lines as per RESPO manual and as per direction of supervising engineer. |
| 42 | LT XLPE/PVC Cable |
| 43 | AB Cable |
| 44 | 11 kv XLPE Cable |
| 45 | ACSR Weasel Conductor |
| 46 | ACSR Dog Conductor |
| 47 | Providing & Fixing of AL Lug |
| 48 | Providing & Fixing of LT Tailless unit |
| 49 | Providing & Fixing of Barbed Wire |
| 50 | Providing & Fixing of Red Oxide Paint |
| 51 | Providing & Fixing of Aluminium Paint |
| 52 | Providing & Fixing of Suspension Clamp |
| 53 | Providing & Fixing of Dead End Clamp |
| 54 | Providing & Fixing of Nut,Bolt & washer |
| 55 | Providing & Fixing of Danger Board |
| 56 | Providing & Fixing of LT Clamp |
| 57 | Providing & Fixing of Different Type of Clamp Please Enable Macros to View BoQ information |