| 1 | A) Erection Part |
| 2 | ERECTION PART 3Ph of LT Line TS NO-406/2023-24 WBS NO-32100261-001-UNA-LT-434 |
| 3 | Erection of LT line. Digging of pit, erection of Steel pole 8 mtr long, erection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 4 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 5 | Erection of Earthing Set.:- Digging of Pit, Fixing of GI Wire To The Earth System and Filling of Pit etc.complete in all respect. |
| 6 | Laying of conductor :- Laying of conductor, striging, sagging and biding with insulator with 7/2.50mm/7/3.15 mm Conductor aug. of New 3-Ph. Re-cond, 7/3.15 mm for 1-Ph. LT complete in all respect., |
| 7 | Laying of G.I Wire, Stringing, Sagging and binding complete in all respect. |
| 8 | Mannual carriage from road to site ,transportation charges from central store to site and loading- unloading in all respect (IN ALL HEAD) average distance at site |
| 9 | ERECTION PART 11/0.4kV,100 KVA Sub-Station underneath TS. N0-405/2023-24 WBS NO- 32100261-001-UNA-DTR-193 |
| 10 | Erection of100 kva S/Stn. Str.:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, Alluminium Paint AI i.e X-arml, Knee bracing set, erection of D-pole,errection of plate form, ercetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Erection of T/F, and earthing conn. to T/F G.O Switch lightning etc. erection of Stay Set, Erection of Jumper, Pipe earthing 3 Nos., Erection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect. |
| 11 | Mannual carriage from road to site ,transportation charges from central store to site and loading- unloading in all respect (IN ALL HEAD) average distance at site |
| 12 | SUPPLY PART |
| 13 | L.T.Line LT Line 3Ph of LT Line TS NO-406/2023-24 WBS NO-32100261-001-UNA-LT-434 |
| 14 | Steel Pole 8 mtr. Long. Provided by HPSEBL |
| 15 | Steel Pole 9 mtr. Long. Provided by HPSEBL |
| 16 | AAAC 7/3.15 mm2 Conductor Provided by HPSEBL |
| 17 | GI Wire Provided by HPSEBL |
| 18 | RCC Muff |
| 19 | Channel Iron (75x40x5) [Length-1.50 Mtr + 0.2 Mtr] |
| 20 | Full Clamp |
| 21 | Half Clamp for Cross Arm |
| 22 | Nut and Bolts |
| 23 | Shackle Insulator with D-Iron |
| 24 | Earth Hook/Eye Hook Bolt |
| 25 | Stay Set Complete (i/c stay clamp) Provided by HPSEBL |
| 26 | Stay Wire (7/3.15mm) (6.0 kg per stay set) Provided by HPSEBL |
| 27 | Earthing Set Complete (preferbly coil earthing) |
| 28 | Aluminium Paint |
| 29 | Red Oxide |
| 30 | Supply PART 11/0.4kV,100 KVA Sub-Station underneath TS. N0-405/2023-24 WBS NO- 32100261-001-UNA-DTR-193 |
| 31 | Distribution Transformer (Ordinary) 11/0.4 KV, 100KVA (Provided By HPSEBL) |
| 32 | Steel Tubular Poles (9 m, Working load>200Kgf/m2) (Provided By HPSEBL) |
| 33 | Muffs with concrete filling |
| 34 | X-Arm (Channel Iron (100X50X6mm) Length 2800mm X 2 No's) for incomer Line. Provided by HPSEBL |
| 35 | MS Angle Iron (50X50X5mm) Length 2800mm x1 No's for LA's . |
| 36 | X-Arm (Channel Iron (75X40X6mm) Length: ( 2800mm x 4 No's) for supporting DO fuse unit & GO switch (Provided By HPSEBL) |
| 37 | Transformer Belting & Knee Bracing |
| 38 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed Provided by HPSEBL |
| 39 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 40 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 41 | MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 42 | MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 43 | Transformer LT Distribution Box and GO Switch fixing Assembly |
| 44 | MS Angle Iron (50X50x6 mm), Length: (2800 mm) x 2 Nos |
| 45 | MS Angle Iron (50X50x6 mm), Length: (450 mm) x 1 Nos |
| 46 | GO Switch Handle Supporting: [Channel Iron (75x40x6 mm), Length: 460 mm |
| 47 | GO AB Switch Unit (11kV, 400A, 25 KA) Tripple pole O/D type |
| 48 | D.O Fuse Unit |
| 49 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 50 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) (Provided By HPSEBL) |
| 51 | Stay set complete |
| 52 | Stay Wire (7/3.15 mm) (7.0 kg per Stay Set) |
| 53 | Pipe Earthing Set |
| 54 | LT Distribution Panel Box with MCCB (50A, 25 kA, 4P) and SFU (16A, 4No, rewirable) |
| 55 | Half Clamp (M.S. Flat 50X6 mm) |
| 56 | Full Clamps (M.S. Flat 50X6 mm) |
| 57 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 58 | Aluminium Thimble |
| 59 | Thimble copper 200 amps |
| 60 | Danger Plate |
| 61 | Barbed Wire |
| 62 | LT Cable (3.5 Core) 185 mm² |
| 63 | Energy Meter (3-Phase, 4-Wire) DLMS compliant 50 A CT Type for 100KVA Transformer |
| 64 | Aluminium Paint. |
| 65 | Prov.Red Oxide (1.5 Ltr. Per Pole) Please Enable Macros to View BoQ information |