| 1 | Strengthening of Mela Theru boys Hostel Road Km 0/0-0/650 in Kannanthangudy EastPanchayat. |
| 2 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. |
| 3 | Earth work excavation and depositing on bank with initial lead of 10metres and lift of 2metres as per SS 20A including breaking clods,sectioning,ramming etc., complete as directed by the dept. officers for formation.(SI. No.61) |
| 4 | Picking the Existing BT Surface 50mm-100mm Thick including cost conveyance and all labour charges for Picking hand packing leveling and consolidation by Power roller rolling including all labour charges and all other insidental charges etc.complete |
| 5 | Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for TOP LAYER |
| 6 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 7 | Applying TACK COAT over Primed WBM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp |
| 8 | BITUMINOUS CONCRETE 25MM THICK USING cmp (Grade-II)Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 |
| 9 | Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 10 | Provision for 60cm Circle Mandatory Sign Speed Limit , U turn Prohibted , Prohibitory signs 80x60 Cn Facility Information Board. |
| 11 | Provision for HM Stone |
| 12 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |