| 1 | Compound Wall |
| 2 | Earthwork excavation for foundation in all soils and sub soils except in hard rock,requiring blasting including shoring and shuttering and bailing out of water wherever necessary,refilling the sides of foundation with excavated earth,well rammed and consolidated with initial lead of 10m & initial lift of 2m and depositing the surplusr earth within the compound in places shown by the departmental officers etc., complete as per Standarad specification SS20B(TNBP No.17,23,24). |
| 3 | Plain Cement Concrete 1:4:8 mix (One Part of Cement, Four Part of Fine Aggregate and Eight Part of Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including cost and conveyance of materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specifications(TNBP No.28). |
| 4 | Supplying and erecting centering for sides and soffits including supports and strutting uptp 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90cmx60cm and 10 gauge stiffened, welded with mild steel angles of size 25mmx25x3mm for boarding laid over silver oak (country wood) joist of size 10cmx6.5cm dia spaced about 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre etc.complete complying with standard specification (TNBP No.30) a) For Grade Beam |
| 5 | For Coloumn |
| 6 | Reinforced Cement concrete 1:1 1/2:3 (One Part of Cement, One and Half Part of Fine aggregate and Three Part of Coarse Aggregate) using 20mm sizeHBGS jelly for all RCC items of work excluding Cost of centering and reinforcement but including cost and conveyance of materials to work site and all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specifications(TNBP No:30) |
| 7 | Supplying, fabricating and placing in position mild steel or ribbed tor steel for all reinforced cement concrete works as per design given including cost of steel and binding wire with all conveyance and lead charges in all floors etc.complete complying with standard specifications- TNBP No:30 |
| 8 | Brick Work in CM 1:5 (One part of cement & five part of Fine aggregates) mix using Second Class Bricks of Size 9 \\" x 4 3/8\\" x 2 ¾\\" including cost and conveyance of materials to work site and including all labour charges for mixing, laying, Finishing and curing etc., complete as per standard specifications – TNBP No:31(Founndation and Basement) |
| 9 | Plastering with CM 1:5 (One part of cement & five parts of M-sand) mix for 12mm thick including cost and conveyance of all materials to work site and including all labour charges for mixing, laying, curing,finishing etc., complete as per standard specifications – TNBP No:56&57 |
| 10 | Painting two coats with ready mixed Plastic Emulsion Paint S.I.358 Plastic emulison paint of'approved quality and colour over a priming coat, including thorough scraping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required including cost and conveyance of all materials etc.and all lobour charges etc.complete as per Standard specificationTNBP No:66-A Please Enable Macros to View BoQ information |