| 1 | Cable lowering and installation of receiving substation at 38L/7D . (Inclusive of EPF/CMPF) |
| 2 | Preparation of 8 nos. wooden clamps of sal wood which will not damaged the sheth of cable (including cost of sal wood) |
| 3 | Fabrication and preparation of 08 nos. of metal clamps for straightening wooden clamp |
| 4 | Installation after transportation of 04 nos. mechanical manual winch at site 10 Te. Capacity |
| 5 | Fabrication and installation heavy duty trangular frame for cable lowering including transportation upto site |
| 6 | 500mtr. Of HT cable lowering i)1st mode cable straight ii)all necessary preparation and lowering of two length (250 mtr. each) of HT cable |
| 7 | Carrying and transportation of 500mtr 150 sqmm HT cable from surafce to underground and laying from borehole location to 38L substaion |
| 8 | VCB-05 nos transport from surface to 38L substation & installation |
| 9 | Transportation & installation of 2 nos lighting panel,couplers, cable entry boxes, M seal compound, lights with cable etc. |
| 10 | LT and HT cable hanging |
| 11 | Liquid M-seal Compound with Hardner (Electrical Installation for splicine cabl from 600V to 69KV) |
| 12 | Steel Wire mesh Braid |
| 13 | Flat Braid Tinned Copper |
| 14 | HT tape |
| 15 | Cello tape |
| 16 | GI wire |
| 17 | Cable lowering and installation of 02 nos belt susbation and one main district susbatation. (Inclusive of EPF/CMPF) |
| 18 | Carrying and transportation of 1300mtr 95 sqmm HT cable from surafce to underground and laying from 38L substation to 71L/8D |
| 19 | Carrying and transportation of 800 mtr 95 sqmm HT cable from surafce to underground and laying from 38L substation to 54L/8D |
| 20 | Carrying and transportation of 500 mtr 95 sqmm HT cable from surafce to underground and laying from 54L/8D substation to 71L subatstation |
| 21 | Carrying and transportation of 300 mtr 95 sqmm HT cable from surafce to underground and laying in RV to RVI drift upto 28No substation |
| 22 | Carrying and transportation of one 6.6Kv VCB from surface and install at bottom of RV to RVI Drift |
| 23 | VCB-01 nos transport from surface to 54L/7D & installation |
| 24 | TSU 01 nos transport from surface and installation at 54L/7D |
| 25 | Transportation & installation of Transwitch Primary VCB and Fitting with Transwitch at 28no substation |
| 26 | Transportation & installation of Transwitch Primary VCB and Fitting with Transwitch at 54L |
| 27 | Transportation & installation of Transwitch Primary VCB and Fitting with Transwitch at 71L substation- 02 nos |
| 28 | VCB-04 nos transport from surface to 71L/8D & installation |
| 29 | TSU 01 nos transport from surface and installation at 71L/8D |
| 30 | ACB 02 nos transport from surface to54L New sub-station & installation |
| 31 | ACB 02 nos transport from surface to 71L new sub-station & installation |
| 32 | Transportation & installation of 2 nos lighting panel,couplers, cable entry boxes, M seal compound, lights with cable etc. |
| 33 | Liquid M-seal Compound with Hardner (Electrical Installation for splicine cabl from 600V to 69KV) |
| 34 | Steel Wire mesh Braid |
| 35 | Flat Braid Tinned Copper |
| 36 | HT tape |
| 37 | Cello tape |
| 38 | GI wire |
| 39 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |