| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming thesides of trenches, levelling, dressing and ramming then bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm. |
| 2 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. (3rd Corrigenda) |
| 3 | Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation.(a) 1:3:6 proportion |
| 4 | Brick work with 1st class bricks in cement mortar (1:6)(a) In foundation and plinth |
| 5 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortarincluding rounding off or chamfering corners as directed andraking out joints including throating, nosing and drip course,scaffolding/staging where necessary (Ground floor).[Excludingcost of chipping over concrete surface] (i) With 1:6 cement mortar (b) 20 mm thick plaster |
| 6 | Neat cement punning about 1.5mm thick in wall, dado, windowsill, floor etc.NOTE:Cement 0.152 cu.m per100 sq.m. |
| 7 | Hire and labour charges for shuttering with centering and necessary stagingupto 4 m using approved stout props and thick hard wood planks of approvedthickness with required bracing for concrete slabs, beams and columns,lintels curved or straight including fitting, fixing and striking out aftercompletion of works (upto roof of ground floor) (f) 25 mm to 30 mm shuttering without staging in foundation |
| 8 | Reinforcement for reinforced concrete work in all sorts of structuresincluding distribution bars, stirrups, binders etc initial straightening andremoval of loose rust (if necessary), cutting to requisite length, hooking andbending to correct shape, placing in proper position and binding with 16gauge black annealed wire at every intersection, complete as per drawingand direction.(a) For works in foundation and upto roof of ground floor/upto 4 m (i) Tor steel/Mild steel I. SAIL/ TATA/RINL |
| 9 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mmnominal size) excluding shuttering and reinforcement if any, in ground flooras per relevant IS codes.(i) Pakur & Chandil Variety |
| 10 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)(a) With earth obtained from excavation of foundation |
| 11 | GST @ 18% |
| 12 | Labour Welfare Cess @ 1% Please Enable Macros to View BoQ information |