| 1 | Dismantling all types of plain cement concrete works, stacking serviceable materialsat site and removing rubbish as directed within a lead of 75 m. In ground floor including roof.. upto 150 mm. thick |
| 2 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. Depth of excavation not exceeding 1,500 mm. |
| 3 | Extra over the above item of Earth work for removing semi liquid mud or slushy earth by iron pans , bucket etc.in excavation |
| 4 | Filling in foundation or plinth by fine sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. |
| 5 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches |
| 6 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes. Pakur Variety |
| 7 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. Pakur Variety In Ground Floor |
| 8 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. For works in foundation, basement and upto roof of ground floor/upto 4 m. Tor steel/Mild Steel. For Ground Floor |
| 9 | Hire and labour charges for shuttering with cantering and necessary staging up to 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works .. 25 mm to 30 mm shuttering without staging in foundation |
| 10 | Hire and labour charges for shuttering with cantering and necessary staging up to 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works. .. Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work |
| 11 | Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall / return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V:20H towards drawing face. Complete as per drawing and Technical specifications. |
| 12 | Supply of UPVC pipes (B Type) & fittings conforming to IS-13592-1992 110 mm |
| 13 | G S T As applicable @ 18% on total work done value ( SL NO. - 1 to 12 ) |
| 14 | Labour Welfare Cess @ 1% on total work done value including G S T ( SL NO. - 1 to 13) Please Enable Macros to View BoQ information |