| 1 | Dismantling (without damage) one km 11kV line (3 conductors), cross arm, insulators, disc, rolling the conductor and stacking. |
| 2 | Transferring LT 3ph 4/5 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
| 3 | Transferring LT Sph 2/3 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
| 4 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials. |
| 5 | Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 6 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 7 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
| 8 | Stringing one km LT Sph 3 wire line (Rabbit for Ph&N, Weasel for St.main) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 9 | Stringing one km LT 3ph 5 wire line (Rabbit for Ph and Weasel for N&St.main) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 10 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon |
| 11 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 12 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |
| 13 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 14 | Dismantling (without damage) LT stay incl. digging pit in all classes of soil and backfilling |
| 15 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 16 | Fitting and erecting one HT PSC Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 17 | Fitting and erecting one HT A type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 18 | Fitting and erecting one HT DP using PSC pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
| 19 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 20 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
| 21 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole incl. digging & back filling pits. |
| 22 | Fitting and providing one Strut using A type pole incl. digging & back filling pit. |
| 23 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
| 24 | Providing one Driven Earth using GI earth pipe at standard distance away from the pole/structure in loose soil. |
| 25 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 26 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 27 | Loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 28 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 29 | Fitting one set AB switch and giving connection Please Enable Macros to View BoQ information |