| 1 | [17.5.3]Compacting Original Ground 3. Compaction of Earthwork Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H specifications [Through Rate] |
| 2 | [21.90.5.5]Construction of rectangular standard brick masonry manhole chambers to standard drawings on S.W. pipe sewers or other circular pipe sewers up to the required depth in 1.5 cement sand mortar, lime concrete in bed and sides of pipe sewer and cement concrete 1:2:4 in benching, 12 mm thick water tight 1:2 cement sand plaster with a floating coat of neat cement and finished with 2 coats of sodium silicate on interior surface where required, reinforced cement concrete slab 180mm thick fixing 560 mm internal diameter C.I. manhole cover and frame weight not less than 2.5 quintal painted with 3 coats of black bitumen paint, fixing galvanised malleable iron steps embedded in 1:2 cement sand mortar complete. the rate covers the cost of M.S. steel for R.C.C. slab labour for fixing and carriage of C.I. manhole frame and cover and malleable iron steps from the stores of the Engineer-in-charge of the works to the site of works. The rate also include the cost of accurately planned and fitted centring, supports for all works as well as for all curves and special work, cleaning out their beds etc. sodium silicate shall be supplied free of cost at the stores of the Engineer-in-charge. 5.5. On 225 mm internal diameter pipe sewer - for 3.00 meters depth below ground level [Through Rate] |
| 3 | [21.97.1]`Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths ISI marked HDPE pipe of PE-100 grade and PN-6 for sewer. application as per IS 14333-1996 (amended up to date) in trenches in complete including cost of HDPE Specials, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications and as per direction of Engineer.Note: E/w to be measured and paid separately. Rate includes cost of all specials like bends, tees required during laying of pipe line along required alignment.` 1. 200 mm Outside Dia [Through Rate] |
| 4 | [3.1.18]By Mechanical Transport including loading, unloading and stacking 18. Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead up to 10 km for all lifts, complete as per directions of Engineer-in-charge. [Rate] |
| 5 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 6 | [6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate] Please Enable Macros to View BoQ information |