| 1 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil |
| 2 | OD285978/2025-2026:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials. All kinds of soil (First Depth) |
| 3 | 5.4:Providing and laying up to floor five level reinforced cement concrete in kerbs, steps and the like excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 4 | 5.7:Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) derived from natural sources derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources derived from natural sources) |
| 5 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 6 | 5.9.12:Centering and shuttering including strutting, etc. and removal of form for:Well steining |
| 7 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 8 | OD286055/2025-2026:Sinking well in all classes of soil other than rock to line and level and plumb by scooping out from inside and below steening including the use of dredgers or any other appliances hire labour for kentledge, getting de watering, blasting vibrating or any other method including removal of obstretics and dumping the soil within a distance of 150 m as per the directions of deptl. officers at site. FIRST DEPTH |
| 9 | OD286054/2025-2026:Sinking well in all classes of soil other than rock to line and level and plumb by scooping out from inside and below steening including the use of dredgers or any other appliances hire labour for kentledge, getting de watering, blasting vibrating or any other method including removal of obstretics and dumping the soil within a distance of 150 m as per the directions of deptl. officers at site. 2 nd DEPTH |
| 10 | OD286053/2025-2026:Sinking well in all classes of soil other than roak to line and level and plumb by scooping out from inside and below steening including the use of dredgers or any other appliances hire labour for kentledge, getting de watering, blasting vibrating or any other method including removal of obstretics and dumping the soil within a distance of 150 m as per the directions of deptl.officers at site. Third depth |
| 11 | OD286052/2025-2026:Sinking well in all classes of soil other than rock to line and level and plumb by scooping out from inside and below steening including the use of dredgers or any other appliances hire labour for kentledge, getting de watering, blasting vibrating or any other method including removal of obstretics and dumping the soil within a distance of 150 m as per the directions of deptl.officers at site.FOURTH DEPTH |
| 12 | OD285977/2025-2026:Supplying cutting and fixing in position 50 mm dia GI pipes for cross bar of the well including all cost conveyance etc |
| 13 | OD285974/2025-2026:Engaging Man coolies including all expenses |
| 14 | 13.71:Lettering with black Japan pint of approved brand and manufacture Please Enable Macros to View BoQ information |