| 1 | Earth work in cutting embeded portion including lift upto 1.50m and lead upto 30m.including cost of driver,POL,maintenance of machine(by poclain/equivalent capacity 60cum/hour i.e.2592 per hour),contractor profit, taxes and T & P etc but excluding leveling,dressing, compaction, required for proper complection of work as per direction of engineer-in charge. |
| 2 | Supplying, laying and placing of 9mm, 4 strands Polypropyline Rope Gabion (1.80mx1.80mx0.50m) with lid only, 150x150 mm mesh size confirming to IS 5175: 1992 (Realfirmed 1997 ) at work site filled with RBM in woven Geo taxtile bags (1.00x0.75m ) ,(>200gsm) standerd as per Is16654:2017 including all cost of materials, labours, T & P and all taxes etc, required for proper completion of work as per direction of engineer-in charge. |
| 3 | Supplying, Laying & Filling of 2m dia and 20m long techtube geotextile tube made of 80 KN Bi-axial strength multifilament woven geo textile(>=330gsm) including all cost of materials,labours,T&P ,all taxes and contractor profit,required for proper completion of work as per direction of engineer-in charge. |
| 4 | Supplying, laying and placing of non woven Geo textile (sheet) of 200 gsm made of 100% polypropylene staple fibre ( continuous filament not allowed) bonded into stable network through needle punching meeting the technical specifications and qualification criteria in the tender the geo textile should be Tech- geo PR15 or equivalent and minimum 70% resistance against UV exposure and should be inert to biological degradation and resistant to naturally occurring acids and alkalies including contractor profit,required for proper completion of work as per direction of engineer-in charge. |
| 5 | Supplying, laying and placing of R.C.C ( Nominal mix 1:1.5:3) porcupine sets binding of murga jali including all cost of materials, labours, T & P with all taxes etc,required for proper completion of work as per direction of engineer-in charge. |
| 6 | Supplying, laying of 4mm/8 SWG G.I.wire for bracing & binding of R.C.C porcupines screen with all fitting complete,including all cost of materials, labours, T & P with all taxes etc,required for proper completion of work as per direction of engineer-in charge. |
| 7 | Supplying and filling jhakhar or jhau (in porcupine set) and placing in position involving carraige upto 5km without boat in dry including all cost of materials,labours, T & P etc,required for proper completion of work as per direction of engineer-in charge. |
| 8 | Earth work in back filling including lift upto 1.50m and lead upto 30m.including cost of driver,POL,maintenance of machine(by poclain/equivalent capacity 60cum/hour i.e.2592 per hour),contractor profit, taxes and T & P etc but excluding leveling,dressing, compaction, required for proper complection of work as per direction of engineer-in charge. Please Enable Macros to View BoQ information |