Name of Work:- Estimate for providing brick pitching and bank strengthening from RD 50500 to 57000 of Saiman Dhanana Link Drain.
Sl. No.
Item Description
1
Ns item is not sanctioned in estimate therefore please do not enter any rate for it.
2
[11.25.2]Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): 2. Raised and cut pointing [Through Rate]
3
[14.18]Filling expansion joints, with special impervious hot pour, 12.5 mm wide. [Through Rate]
4
[14.2]Dressing side slopes and preparation of sub grade for lining by mechanical/ mannual means [Through Rate]
5
[4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate]
6
[4.33]Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 1 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. [Through Rate]
7
[6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate]
8
[6.22.1.3]Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plain cement concrete work, including pumping of R.M.C. from transit mixer to site of laying and curing, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer-in-charge. 1.3. All works above plinth and up to floor IV level : M-10 grade plain cement concrete (cement content considered @ 220 kg/cum) [Through Rate]
9
[6.29.1]Centering and shuttering including strutting, propping etc. and removal of form work for : 1. Foundations, footings, bases for columns [Through Rate]
10
[7.22.3]Brick work with common burnt clay non-modular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 3. Cement mortar 1:3 (1 cement : 3 coarse sand) [Through Rate] Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.