| 1 | water tank maintanance |
| 2 | 15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. |
| 3 | 14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done . |
| 4 | 50.10.1:Steel work in built up G I tubular ( round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting,fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete |
| 5 | 50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete |
| 6 | OD420144/2025-2026:Providing and fixing Alu Zinc profile sheets (size, shape and pitch of corrugation asapproved by engineer in charge) 0.40 mm(+0.05%) thickness. Sheet should have protectiveguard film of25microns minimum to avoid scratches during transportation and should be supplied in a singlelength of 12 M or as decide by the Engineer in charge. The sheets shall be fixed using selfdrilling / self tapping screw of size (5.5x55 mm) with EPDM seal complete upto any pitch inhorizontal/ vertical/ curvedsurface, but excluding the cost of purlins, rafters, trusses, and including cutting to size shapeswhere ever required. (MOD 12.50 of DSR) |
| 7 | 13.17:6 mm cement plaster 1:3 ( 1 cement : 3 fine sand) finished with a floating coat of neat cement and thick coat of Lime wash on top of walls when dry for bearing of R.C.C. slabs and beams. |
| 8 | 14.1.1:Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground within 50 meters lead:With cement mortar 1:4 ( 1 cement : fine sand) |
| 9 | 22.23.1:Providing and applying integral crystalline slurry of hydrophilic in nature forwaterproofing treatment to the RCC structures like retaining walls of the basement,water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 partsintegral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 partsintegral crystalline slurry : 1 part water) for horizontal surfaces and applying thesame from negative (internal) side with the help of synthetic fiber brush. The materialshall meet the requirements as specified in ACI-212-3R-2010 i.e by reducingpermeability of concrete by more than 90% compared with control concrete as perDIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystallineslurry shall be capable of self-healing of cracks up to a width of 0.50mm. The workshall be carried out all complete as per specification and the direction of the engineerin-charge. The product performance shall carry guarantee for 10 years against anyleakage.For vertical surface two coats @0.70 kg per sqm |
| 10 | 22.23.2:Providing and applying integral crystalline slurry of hydrophilic in nature forwaterproofing treatment to the RCC structures like retaining walls of the basement,water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 partsintegral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 partsintegral crystalline slurry : 1 part water) for horizontal surfaces and applying thesame from negative (internal) side with the help of synthetic fiber brush. The materialshall meet the requirements as specified in ACI-212-3R-2010 i.e by reducingpermeability of concrete by more than 90% compared with control concrete as perDIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystallineslurry shall be capable of self-healing of cracks up to a width of 0.50mm. The workshall be carried out all complete as per specification and the direction of the engineerin-charge. The product performance shall carry guarantee for 10 years against anyleakage.For horizontal surface one coat @1.10 kg per sqm. |
| 11 | 13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer |
| 12 | 13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work Please Enable Macros to View BoQ information |