| 1 | Earthwork excavation for foundation in all soils and sub soils in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders and to full depth as may be directed,except in hard rock,requiring blasting including shoring and shuttering and bailing out of water wherever necessary,refilling the sides of foundation with excavated earth or sand in layer of not more than 15cm thick.well rammed and consolidated and depositing on bank with initial lead and lift of 10m & initial lift of 2m and depositing the surplusr earth within the compound in places shown by the departmental officers with iniital lead and lifts,clearing and levelling the site etc., complete as per SS20B and as directed by departmental Engineers(TNBP No.17,23,24). |
| 2 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 3 | Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). |
| 4 | Supplying and erecting centering for sides and soffits including supports and strutting uptp 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90cmx60cm and 10 gauge stiffened, welded with mild steel angles of size 25mmx25x3mm for boarding laid over silver oak (country wood) joist of size 10cmx6.5cm dia spaced about 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre tocentre etc.complete complying with standard specification and as directed by the departmental engineers. (TNBP No.30) |
| 5 | Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors. |
| 6 | Reinforced Cement concrete 1:1.5 :3 (one cement, one and half M.sand & three course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete. |
| 7 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9\\" X 43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 8 | Plastering with cement mortar 1:4 (One Part of Cement and Four part of Plastering Sand (P- Sand)) 12mm thick in all floors including cost and conveyance of all materials to site and labour charges etc, complete complying with standard specifications (S.I.309) |
| 9 | Supplying and laying in flooring with fully polished Sinthetic Grey colour Granite stone of 20mm thick (average) of 4' X 2' in size laid over base layer of cementmortar 1:3 (one cement and three Plastering sand) - 20 mm thick and applying cement slurry &pointed with white cement and colour pigments to the colour of stones and polished neatly as directed by the deparmental officers |
| 10 | Fabrication, Supplying and Fixing of Stainless Steel Bus Shelter Light Roofing Arrangement of size 9.00m x 2.40m using 100mm dia 304L Grade Stainless Steel pipe of continuos profile as shown in Elevation 1.60mm thick at required locations to a height of 3300mm from finished floor level . The Light Roofing is made up of Stainless Sheet 6mm thick.The rate is inclusive of the charges for cutting, bending, welding, grinding, polishing, conveyance, electrical charges, etc. complete |
| 11 | Manufacturing, Supplying and Fixing of Stainless Steel Hand rails for staircase using 50mm dia 304L Grade Stainless Steel pipe of 1.60mm thick at required locations to a height of 900mm from finished floor level welded to 38mm dia Stainless Steel pipe post of 1.00mm thick as vertical at 900mm centre with 2 Nos. of 25mm dia intermediate horizontal stainless steel pipe of 1.60mm thick in between. The vertical pipe has to be welded to the 100 X 100 X 6mm MS base plate encased in the base concrete. The rate is inclusive of the charges for cutting, bending, welding, grinding, polishing, conveyance, electrical charges, etc. complete |
| 12 | GST 18% Please Enable Macros to View BoQ information |