| 1 | Fitting and erecting one HT A typeSingle Pole in position, including fittingcross arm, digging and back filling pit inordinary soil (as per standards), drawingsufficient length of GI earthing leadsfrom F clamp through V cross arm to theground for earthing (excluding provisionof earthing). |
| 2 | Labour charges for loading HT A typepole from the stacking place andunloading the same at work site(transportation by any vehicle). |
| 3 | Providing concrete muffing of size0.45x0. 45x1.5m (0.5m above GL and1m below GL). Excavation0.45x0.45x1m, concrete (1:3:6, 20mm)0.45x0.45x1.5m, Plastering (1:3) 12mm0.45x0.45mx5sides. |
| 4 | Fitting one set AB switch on existingDP, giving connection and drawingsufficient length of GI earthing leads tothe ground for earthing, excludingprovision of earthing. |
| 5 | Fitting one Additional 2.4m/3m Channelcross arm (100x50x6mm), in existing11kV DP including conveyance ofmaterials. |
| 6 | Fitting and erecting one HT Double PoleStructure using PSC pole in positionincluding fitting 2 channel cross arms,digging and back filling pit in ordinarysoil, drawing sufficient length of GIearthing leads through all cross arms tothe ground for earthing (excludingprovision of earthing). |
| 7 | Labour charges for loading HT PSC polefrom the stacking place and unloadingthe same at work site (transportation byany vehicle). |
| 8 | Stringing of one km 11kV line withACSR Raccoon (3 conductors) after fitting insulators and giving jumperconnections including cutting andremoving tree branches wherevernecessary excluding cut point works. |
| 9 | Fitting and erecting one HT PSC SinglePole in position, including fitting crossarm, digging and back filling pit inordinary soil (as per standards), drawingsufficient length of GI earthing leadsfrom F clamp through V cross arm to theground for earthing (excluding provisionof earthing). |
| 10 | Additional rate for providing one discset, PG clamp etc. complete, on any typeof HT pole for making cut point. |
| 11 | Fitting one Additional 75x40mm, 1.8mChannel cross arm in existing single poleincluding conveyance of materials. |
| 12 | Fitting one Additional V cross arm inexisting single pole includingconveyance of materials. |
| 13 | Providing one Driven Earth using GIearth pipe of size 38.1mm dia, 2.5mlength at minimum distance of 1.5maway from the pole/structure andmaintaining standard distance betweendifferent earth pipes in loose soil. |
| 14 | Providing one Earth using GI earth pipeof size 38.1mm dia, 2.5m lengthincluding digging separate pit(0.45x0.45x2.5m) at a minimumdistance of 1.5m away from thepole/structure and maintaining standarddistance between different earth pipes inordinary soil & backfilling. |
| 15 | Dismantling (without damage) one LTPSC/RCC pole after disconnecting stays,strut etc. attached thereon and stackingthe same. |
| 16 | Dismantling (without damage) one kmLT three phase 4 wire OH line conductorby dismantling cross arms, insulatorsand stacking the conductors in rollsproperly. |
| 17 | Transferring LT three phase 4/5 wire OHline to newly erected HT/LT poleincluding dismantling existing cross armand insulators, refitting the same on thenew pole, binding etc. complete. |
| 18 | Disconnecting and lowering down thesingle phase WP service connection withguy wire from the OH line andreconnecting the same after completing the line work. |
| 19 | Disconnecting and lowering down thethree phase WP service connection withguy wire from the OH line andreconnecting the same after completingthe line work. |
| 20 | Reshackling one span LT three phase 4wire OH line including pin binding,jumpering, replacing insulators/crossarms/shackle, tightening stay, cuttingtree branches etc. wherever necessaryincluding conveyance of all materials. |
| 21 | Dismantling one ordinary streetlight/CFL/LED fitting from existing poleand refitting the same on newly erectedpole including disconnecting andreconnecting wires. |
| 22 | Reshackling one span LT single phase 2wire OH line including pin binding,jumpering, replacing insulators/crossarms/shackle, tightening stay, cuttingtree branches etc. wherever necessaryincluding conveyance of all materials. |
| 23 | Cutting trees having girth beyond 60cmbut upto and including 120cm, inbetween the line and Buildings wherespace for falling trees is notavailable/enough (felling trees includingcutting of trunks and branches) andremoving the root completely andstacking etc. 1 No. |
| 24 | Cutting trees having girth beyond 120cmbut upto and including 180cm (fellingtrees including cutting of trunks andbranches) and removing the rootcompletely and stacking etc. 1 No. |
| 25 | Drilling hole of various sizes on existingChannel/Cross Arm. |
| 26 | Fitting and providing one HT Stay for11kV pole, including digging and backfilling pit in ordinary soil. |
| 27 | Fitting and providing one Strut using HTPSC pole including digging and backfilling pit in ordinary soil. |
| 28 | Fitting and providing one HT Fly stayfor 11kV pole using HT PSC poleincluding digging and back filling pits inordinary soil, drawing sufficient lengthof GI earth leads to the ground forearthing (excluding provision ofearthing). |
| 29 | Transporting poles by hired vehicle to adistance upto 5km and carrying upto 4 numbers of poles excluding loading&unloading charges. |
| 30 | Providing one Coil Earth using No.8 GIearth wire (50mm dia, 115 turns)including digging separate pit(0.45x0.45x1.5m) at standard distanceaway from the pole/structure in ordinarysoil & backfilling. |
| 31 | Fitting and erecting one HT Double PoleStructure using A type pole in positionincluding fitting 2 No. channel crossarm, digging and back filling pit inordinary soil, drawing sufficient lengthof GI earthing leads through all crossarms to the ground for earthing(excluding provision of earthing). |
| 32 | Installing one DTR Meter with box(normal size 40x25x100cm) on existingpoles including fixing of 3 CTs on busbar, laying and termination of controlcable using proper lugs, fixing of meters,capacitors, control fuses and giving thecomplete connections includingconveyance of materials. |
| 33 | Fitting 3 channel cross arms, AB switch,DO fuse, LA(Ord), HT & LTconnections upto OH lines, etc. onexisting DP structure, fixing distributionbox/provision for one set (3No.) of LTfuses, drawing sufficient length of GIearthing leads to the ground for earthing,excluding provision of earthing &mounting of Transformer on plinth. |
| 34 | Additional rate for refitting/redoing oneShackle Set, including reshacling onespan, while renewing any type of LTpole. |
| 35 | Erection of LT 3 way distribution box(normal size 160x40x90cm) on existingcross arm, giving connection includingcable and earth connection (excludingearthing). |
| 36 | Fitting one Additional 2.4/3m Channelcross arm (75x40x6mm), in existing11kV DP including conveyance ofmaterials. |
| 37 | Providing Transformer fencing to aheight of 1.8 m above ground level usingMS Angle frames of size ISA50x50x6mm for outer frame, 2 runs of40 x 6 MS flat for horizondal brasingand grills with MS rods 8 mm Dia @10cm c/c for verticals, providing gatewith locking arrangements, providing danger board & name board, embedingthe legs in cement concrete 1:2:4,footing of size 30cmx30cmx50cm,painting with synthetic enamel paint twocoats over one coat of iron primer etccomplete, incl cost of transportation |
| 38 | Cleaning and levelling of transformeryard/RMU, spreading 40 mm brokenstone in yard for a thickness of 10 cmabove bed of 10 cm thick 6 mm brokenstone, after constructing a curb wall ofheight 20cm above ground and 10cmbelow level including cost of allmaterials and charges for conveying,spreading, consolidating etc. |
| 39 | Erecting one 100kVA Transformer toexisting DP and giving connections,including loading from TMR/SRS/otherstacking place & unloading at site butexcluding cost for transportingtransformer. |
| 40 | Transporting Transformers by hiredvehicle to a distance upto 5km andcarrying upto 2 numbers of63/100/160/250kVA Transformers /Ring Main Units excluding loading&unloading charges. |
| 41 | Transporting Transformers by hiredvehicle to a distance beyond 5km andcarrying upto 2 numbers of63/100/160/250kVA Transformers /Ring Main Units (Running km). Please Enable Macros to View BoQ information |