| 1 | Earth work in cutting or in embankment in ordinary soil, excavation to be in the form of regular pit not exceeding 1/2 metre (20'') in depth and earthwork in embankment to be 20 cm (8'') layers including ramming and dressing the surface to required levels and slopes and also including 1.5 mts lead. The earth form cutting to be used in making embankment or to be desposited on spoil banks within 30 m. (100 ft.) distance as directed by the Engineer-in-charge Excluding Royalty. (As per SOR 253) |
| 2 | Brick soling on straight over burnt bricks laid on edge and dry (labour only) including preparation of sub grade to prescribed camber filling joints with local earth sreading blinding coat 1cm.(3/8'')depth of local earth over the entire surface & including labour and T&P etc. required for proper completion of work 100 sft. Preparation of sub grade. As per PWDSOR CH: 20 (785) |
| 3 | Earth Work in annual repairs with dressing by any means, lead up to 30 m. And lift up to 1.50 |
| 4 | Providing and fixing boundary piller at Badel dy. |
| 5 | Levelling & Dressing of service road. |
| 6 | Vleaning thick jungle and thotney bushes without uprooting. |
| 7 | Demolishing Brick Work in cement Mortar Manually/ by Mechanical means i/c stacking of steel bars and disposal of unserviceable material within 50 m lead as per direction of Engg. - in - charge. |
| 8 | E/W in cutting in foundation of box Culvert/guide wall on channels including lead upto 30 M and lift upto 1.5 M and disposal and back filling as per direction of Engineer - in - Charge |
| 9 | Laying Plain Cement Concrete in foundation including cost of material, labour, T&P etc. Complete |
| 10 | Laying Plain Cement Concrete 1:2:4 (M-15) in foundation including cost of material, labour, T&P etc. Complete |
| 11 | Laying Reinforced Cement Concrete 1:1:2 (M- 25)in Foundation , wall slab etc with stone grit including cost of material , labour T&P etc. complete |
| 12 | Bending, Binding,Cutting and Placing in postion Reinforcement including cost of all material, labour and T&P etc. required for proper completion of work. |
| 13 | Centering and shuttering for C.C.& RCC work other than building including all material labour and t&p etc. for proper completion of work. |
| 14 | Providing & fixing 110 mm dia PVC drainage spouts including cost of all material, labour T&P etc. complete |
| 15 | Providing & fixing 75 mm dia PVC weep holes including cost of all material, labour T&P etc. complete |
| 16 | Supply and laying 25 mm thick joint filler board in expansion joint in slab. |
| 17 | Providing and fixing wheel guard of RCC 1:2:4 of size 0.20*0.20*0.75 including cost of all Material labour and T&P required for completion of work. Please Enable Macros to View BoQ information |