| 1 | Item No.1 Excavation for foundation/pipe trenches in earth, soils of all types, sand, gravel and soft murum, hard murum and boulders, WBM roads, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete (MJP DSR 2023-24, Page No.37, Avg. of Item No.1, 2&3 with 10% extra for Hilly area) |
| 2 | Item No.2: Excavation for foundation/pipe trenches in soft rock and old cement and lime. masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking as directed by Engineer-incharge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete , Item No.5, with (MJP DSR 2023-24, Page No.37 10% extra for Hilly area) |
| 3 | Item No.3: Providing and laying in situ Cement Concrete M-15 of trap/ granite/quartzite / gneiss metal for foundation and bedding including bailing out water, form work, compaction, curing, etc. complete. (MJP DSR 2023-24, Page No.47, Item No.1(b), with 10% extra for Hilly area) |
| 4 | Item No.4: Providing second class Burnt Brick masonry with conventional/ I.S. type bricks in cement mortar 1:6 in superstructure including striking joints, raking out joints, watering and scaffolding etc. Complete (PWD DSR 2023-24, Page No.199, Item No.27.05, with 10% extra for Hilly area on labour part) |
| 5 | Item No.5: Providing internal cement plaster 20mm thick in Single coats in cement mortar 1:4 without neeru finish, to concrete, brick surface, in all positions including scaffolding and curing etc. Complete (PWD DSR 2023-24, Page No.211, Item No.32.07, with 10% extra for Hilly area on labour part) |
| 6 | Item No.6: Providing and fixing in position steel fibre reinforced concrete (S.F.R.C.) frame and covers of approved make including loading, unloading, transportation, all taxes, etc. complete as directed by Engineerin-charge (560 mm dia.) For Leach pit-Size 600 mm Dia. |
| 7 | Item No.7:For Sedimentation tank - Size 0.90 x 0.45 m (MJP DSR 2023-24, Page No.288, Item No.17(c), with 10% extra for Hilly area) |
| 8 | Item No.8: Providing and laying and fixing P.V.C. pipe of 110 mm dia. 4 kg/cm² pipe With fitting, including cost of pipe, fitting material, labour, --- do etc. complete. (MJP DSR 2023-24, Page No.74 to 78, Item No.1 & 4, with 10% extra for Hilly area on labour part) |
| 9 | Item No. 9: Providing soling using 80 mm trap metal for foundation and bedding including dewatering formwork, competing and curing etc. Complete (MJP DSR 2023-24, Page No.41, Item No.18, with 10% extra for Hilly area) |
| 10 | Item No.10: Total Cost Of Leach Pits For ( Total 3 Leach Pits Plus Above Discription Mention) |
| 11 | Item No. 11: Providing convenience PVC Pipe Line Please Enable Macros to View BoQ information |