| 1 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. |
| 2 | Providing coarse clean sand in filling in in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume) |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete |
| 6 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I |
| 7 | Providing and laying with good quality of boulder duly packedas per specification and direction of E/I. |
| 8 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 40 mm nominal size) |
| 9 | Providing randam rubble stone masonry in CM (1:4) in foundation and plinth with hammer dressed stone of less than 0.03 M3 in volume and clean coarse sand of F.M. 2 to 2.5 including cost of screening raking out joints to 20 mm depth, curing taxes and royalty all complete as per building specification and direction of E/I. |
| 10 | Providing randam rubble stone masonry in CM (1:4) in superstructureincluding cost of screening of materials scaffolding raking out joints to 20 mm depth, curing taxes and royalty all complete as per building specification and direction of E/I. |
| 11 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) |
| 12 | Providing weep holes with dry grade stone filter of 20mm to 40mm size in abutment and wing wall as per specification and direction of E/I |
| 13 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete |
| 14 | Earth work in filling in foundation trenches or back filling of masonry structure with state earth in layer not exceeding 150mm thick well watered rammed and fully compacted and finely dressed with earth obtained from excavation of foundation trenches and kept at a lead of 30m and initail lift 1.5m complete as per specification and direction of E/I. |
| 15 | Carriage of Materials :-i) Cement - |
| 16 | ii) Sand - |
| 17 | iii) Stone Chips - |
| 18 | iv) Stone Metal - |
| 19 | v) Boulder |
| 20 | Good and Services Taxes @ 18% |
| 21 | Labour Cess @ 1% Please Enable Macros to View BoQ information |