| 1 | Clearing and Grubbing Road land (Clearing and Grubbing Road land including uprroting rank vegetation, grass, bushes, shrubs, sapling and trees grith up to 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials to be used or auctioned up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness |
| 2 | Granular Sub base with coarse graded material (Table 400-2) (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place mithoe with rotavatory at OMC, and compacting with vibratory roller to achieve the desire density, complete as per clause 401) for Grading-ii Material. |
| 3 | Providing RCC M 20 in nominal mix (1:1.5:3) in Foundation with approved quality of stone chips 20mm to 6mm size graded and clean course sancl of F.M 2.5 to 3 including screening, Mixing cement concrete in mixer and placing in position vibrating, striking, curing, taxes and royalty all complete as per specification and direction Engineer-in-charge |
| 4 | Filling in foundation trenches and pinth in layers not exceeding 150mm tick well watered, rammed, fully compacted and fine cressed with earth obtained from excavation foundation treches within a alead of 50M and lift of 1.5 mm. All complete as per building dpecification and direction of E/I (Mode of measurement compacted volume). (Final Filling) |
| 5 | Providing shuttering including stretting propinng etc and its removal after use in foundation as per …do…do |
| 6 | Earth work in excavation in foundation of structers as per drawing ……….do…..do E/I |
| 7 | Providing sand filling in faundation and trenchy do….do… E/I |
| 8 | Providing and laying potling laid stone boulder soling do…..do…. E/I |
| 9 | Providing PCC M-150 in faundation do…..do…. E/I |
| 10 | Providing stone masonary work in cm (1:4) in foundation do………do. E/I. |
| 11 | Providing R.C.C M-200 in deack slab and bed plate do………do. E/I. |
| 12 | Providing masanary work in cm (1:4) in S/S do………do. E/I. |
| 13 | Providing PCC M-150 in top of paraput and wearing coat do………do. E/I. |
| 14 | Providing Centering and shuttring do…..do…….E/I |
| 15 | Providing 25 mm tick e.f. in cm (1:4) with 1.5 m punning do………do. E/I. |
| 16 | Providing M.S reinforcement qty. same Iten No.-6 |
| 17 | Carriage of Materiala) Cement and steel lead 10 km |
| 18 | b) sand leed 2+65km |
| 19 | c) stone chips lead 2+15km |
| 20 | d) stone boulder lead2+15km |
| 21 | iv) Earth lead 1 km |
| 22 | v) Dust (Aggregate for GSB) 2+15km |
| 23 | Good and Services Taxes @ 18% |
| 24 | Labour Cess @ 1% Please Enable Macros to View BoQ information |