| 1 | WBM Grading 3 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. By Mechanical Means |
| 2 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. |
| 3 | 20 mm thick Open Graded Premix Carpet using Bitumen Emulsion as per Technical Specification Clause 508.2 |
| 4 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 Bitumen (VG-10) |
| 5 | Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer- in- charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction |
| 6 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. As per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction |
| 7 | Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses702, 704, 1202 & 1203 of MORD Specifiction |
| 8 | Hand Packed stone filling in back of wallls including cost of all materials, royality, T&P etc. complete as per direction of Engineer-in-charge. (As per PWD Uttarakhand specifications) |
| 9 | Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 (For height upto 5 m) PCC 1:3:6 |
| 10 | White washing of parapet walls of CD work and tree truncks White washing two coats on parapet walls and tree trunks including preparation of surface by cleaning scraping etc. as per technical specifications Clause 1915 |
| 11 | Maintenance of Drains The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as well as catch water drains as per technical specification Clause 1907. |
| 12 | Maintenance of Earhen shoulder (stripping of excess soil)Stripping excess soil from the shoulder surface to achieve the approved leveland compacting with plate compactor at OMC as per drawings and Technical Specification Clause 1903 |
| 13 | Construction of coolie walling including supply of all material, labour, T&P etc. required for proper completion of the work as per direction of Engineerin- charge. (As per PWD Uttarakhand specifications) Please Enable Macros to View BoQ information |