| 1 | HT line (Supply Part) |
| 2 | Supply of 9.00 Mtr. Long ISI marked swaged steel tubular pole as per IS: 2713/1980 (Part-'A') as amended from time to time, along with Cap Welded on top & Cast iron Base plate of designation 410SP-47 |
| 3 | Supply of 10:00 Mtr. Long ISI marked swaged steel tubular pole as per IS: 2713/1980 (Part-'A') as amended from time to time, along with Cap Welded on top & Cast iron Base plate of designation 410SP-47 |
| 4 | Supply of RCC muff |
| 5 | Supply of ACSR 6/1/4.72 Sqm |
| 6 | Supply of LT stay set & with Stay wire complete in all respect |
| 7 | Supply of Nuts and Bolts |
| 8 | Supply of MS Channel iron (100x50x6mm), Length: 2800 mm x2 nos |
| 9 | Supply M.S.A.I Bracing set (2125x50x50x6)2mm |
| 10 | Supply Ms Anglre Iron (50x50x6mm) Length: 2800, 2Nos |
| 11 | Supply X-Arm Channel Iron (75x40x5mm), Length: 2800 |
| 12 | Supply Anchoring Assembly for HT |
| 13 | Supply MVT Connector |
| 14 | G.O. Switch Handle supporting C.I. (75x40x6) Length 460mm |
| 15 | Prov. G.O. Switch Unit (11KV, 400A, 25 kA) |
| 16 | Prov. D.O Fuse Unit |
| 17 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 18 | 11kV Pin Insulator |
| 19 | Prov. Half Clamp |
| 20 | Prov. Full Clamp |
| 21 | Erection Part |
| 22 | MANUAL CARRIAGE OF 9/10:00 Mtr. Pole FOR 1KM HT LINE AVERAGE DISTANCE FROM ROAD HEAD TO SITE OF WORK (AVERAGE LEAD=0.3KM) |
| 23 | Erection of steel tubular pole complete viz digging of pit, Erection of pole, Fixing of insulator, Concreting of RCC Muff, Filling of pit+ramming, painting of pole and all steel items (Punching of the poles is stricitly not allowed) |
| 24 | Erection of steel tubular pole (Six pole str. ) digging of pit, Drilling of holes in X- Bracing Set, X-arm, Erection of pole, Fixing of insulator X-arm X-Bracing Set, Fixing of barbed wire danger plate , Concreting of RCC Muff, Filling of pit+ramming, painting of pole and all steel items (Punching of the poles is stricitly not allowed) |
| 25 | Laying sagging & binding of ACSR 6/1/4.72 Sqmm |
| 26 | R-stringing , Re-sagging & binding of ACSR 6/1/4.72 Sqmm |
| 27 | Sagging Of AB Cable |
| 28 | Installation of Suspension anr tension assembly etc. |
| 29 | Erection of Do fuse |
| 30 | Erection of GO Switch |
| 31 | Erection of Stay Set LT (Digging of pit, fixing of stay rod, filling of pit , nozzeling & tighting) Please Enable Macros to View BoQ information |