| 1 | A) Erection Part |
| 2 | ERECTION PART 11kV HT Line |
| 3 | Erection of S.T Two Pole Str. 11 Mtr. Long :- Digging of Pit fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit , Alluminium Paint and ramming & painting of poles complete in all respect. |
| 4 | Stringing and sagging conductor:- Laying of conductor stringing and sagging, binding with insulator complete in all respect. |
| 5 | Laying of G.I Wire, Stringing, Sagging and binding complete in all respect. |
| 6 | Fixing of earthing pipe of pit for coal earthing, fixing of G.I wire to system filling of pit and remaning work complete in all respect. |
| 7 | Erection of Stay Set HT:- Digging of Pit fixing of Stay Rod, filling of Pit, Nozeiling & Tightning complete in all respect. |
| 8 | Mannual carriage from road to site ,transportation charges from central store to site and loading- unloading in all respect (IN ALL HEAD) average distance at site |
| 9 | ERECTION PART 11/0.4kV,63 KVA Sub-Station |
| 10 | Erection of63 kva S/Stn. Str including dismentled existing 11/0.4kv,63 kva Sub-Station and shifted to another site .:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, Alluminium Paint AI i.e X-arml, Knee bracing set, erection of D-pole,errection of plate form, ercetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Erection of T/F, and earthing conn. to T/F G.O Switch lightning etc. erection of Stay Set, Erection of Jumper, Pipe earthing 3 Nos., Erection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect. |
| 11 | Supplying and fixing wovenplains G.I. Wire fencing of mash 50x150mm (Aproximate quantity 24 m2) icluding vertical post 2 mtrs. ISA hight and 0.60mtrs. embeded in concrete 1:2:4 (6Nos) ISA 65x65x6 mm & steel gate including all fitting (approximate weight 30 Kg. ) complete. |
| 12 | Mannual carriage from road to site ,transportation charges from central store to site and loading- unloading in all respect (IN ALL HEAD) average distance at site |
| 13 | SUPPLY PART. 11kV HT Line |
| 14 | Prov. Steel Tublar 11 mtr long with cap. (Provided By HPSEBL) |
| 15 | Prov. RCC Muff |
| 16 | Prov.AAAC 7/4.26 mm Conductor (Provided By HPSEBL) |
| 17 | Prov.G.I.Wire No. 8 SWG in mtr. (Provided By HPSEBL) |
| 18 | Prov.X-Bracing Set.MS Angle Iron (50x50x6 mm) Length 2125 mm x2 Nos. |
| 19 | Prov.X-Arm (Horizontal) MS-Channel Iron (100x50x6mm) Length 2340 mm x2 Nos. ( ∆) Formation. |
| 20 | Prov. MS Channel Iron (75x40x6 mm) Length 2800 mm |
| 21 | MS Channel Iron (75x40x6 mm) Length 2800 mm for holding the 11kv G.O.Switch handle |
| 22 | G.O. Switch Handle Supporting (Channle Iron 75x40x6 mm) Length 460mm |
| 23 | Prov.GO AB Switch Unit (11kV, 400A, 25 KA ) |
| 24 | Prov.D.O Fuse Unit |
| 25 | Prov.Nuts and Bolts of Various Sizes |
| 26 | Prov.MS Half Clamp (Provided By HPSEBL) |
| 27 | Prov.MS Full Clamp |
| 28 | Prov.Barbed Wire |
| 29 | Prov.Eye/Earth Hook |
| 30 | Prov.11kv Pin Insulator with pin complete in all respect |
| 31 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) (Provided By HPSEBL) |
| 32 | Prov.11kv Stay Set |
| 33 | Prov. Stay Wire (7/3.15 mm) (10 kg. per Stay Set) |
| 34 | Prov.11kv Earthing set complete in all respect. |
| 35 | Prov.Red Oxide (1.5 Ltr. Per Pole) |
| 36 | Prov.Alluminum Paint |
| 37 | Prov.11kv Danger Plate (250x200x1.6 mm) |
| 38 | SUPPLY PART |
| 39 | Supply PART 11/0.4kV,63 KVA Sub-Station |
| 40 | Distribution Transformer (Ordinary) 11/0.4 KV, 63KVA (Provided By HPSEBL) |
| 41 | Steel Tubular Poles (9 m, Working load>200Kgf/m2) (Provided By HPSEBL) |
| 42 | Muffs with concrete filling |
| 43 | X-Arm (Channel Iron (100X50X6mm) Length 2800mm X 2 No's) for incomer Line. Provided by HPSEBL |
| 44 | MS Angle Iron (50X50X5mm) Length 2800mm x1 No's for LA's . |
| 45 | X-Arm (Channel Iron (75X40X6mm) Length: ( 2800mm x 4 No's) for supporting DO fuse unit & GO switch (Provided By HPSEBL) |
| 46 | Transformer Belting & Knee Bracing |
| 47 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed Provided by HPSEBL |
| 48 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 49 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 50 | MS Angle Iron (35X35x5 mm), Length : (460 ) x 2 Nos |
| 51 | MS Angle Iron (50X50x6 mm), Length : (950 mm) x 2 Nos for Bed Knee Bracing |
| 52 | Transformer LT Distribution Box and GO Switch fixing Assembly |
| 53 | MS Angle Iron (50X50x6 mm), Length: (2800 mm) x 2 Nos |
| 54 | MS Angle Iron (50X50x6 mm), Length: (450 mm) x 1 Nos |
| 55 | GO Switch Handle Supporting: [Channel Iron (75x40x6 mm), Length: 460 mm |
| 56 | GO AB Switch Unit (11kV, 400A, 25 KA) Tripple pole O/D type |
| 57 | D.O Fuse Unit |
| 58 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 59 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) (Provided By HPSEBL) |
| 60 | Stay set complete |
| 61 | Stay Wire (7/3.15 mm) (7.0 kg per Stay Set) |
| 62 | Pipe Earthing Set |
| 63 | LT Distribution Panel Box with MCCB (40A, 25 kA, 4P) and SFU (16A, 4No, rewirable) |
| 64 | Half Clamp (M.S. Flat 50X6 mm) |
| 65 | Full Clamps (M.S. Flat 50X6 mm) |
| 66 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 67 | Aluminium Thimble |
| 68 | Thimble copper 200 amps |
| 69 | Danger Plate |
| 70 | Barbed Wire |
| 71 | LT Cable (3.5 Core) 70 mm² |
| 72 | Energy Meter (3-Phase, 4-Wire) DLMS compliant 50 A CT Type for 100KVA Transformer Provided by HPSEBL |
| 73 | Aluminium Paint. |
| 74 | Prov.Red Oxide (1.5 Ltr. Per Pole) Please Enable Macros to View BoQ information |