| 1 | Excavation in foundation in ordinary soil (Loam clay or sand) including lift upto 1.50 M and lead upto 30.00M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer incharge upto a distance of 30m from the foundation trenches (where machine con not reach/move) (SOR-20/251 (A)/4.1.1) |
| 2 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm. depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth with lead upto 50 metres. (DSR-18/16.1) |
| 3 | Granular sub-base with graded material, plant mix method Construction of granular sub-base by providing close graded material, mixing in a mechanical mix plant at OMC, carriage of mixed material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. MORTH/4.01/401(A) |
| 4 | Wet mix macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with grader in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density (MORTH/4.14/406(B)) |
| 5 | Brick edging in full brick width and half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres. |
| 6 | With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 (DSR-18/16.7.1) |
| 7 | Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. (MORTH 502/5.01/A(i)) |
| 8 | Providing and applying tack coat with bitumen grade of VG-10 using pressure distributor at the rate of 0.50 Kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (MORTH 5.02/503) |
| 9 | Providing and laying dense graded bituminous macadam with Higher capacity batch type HMP using crushed aggregates of specified grading Premixed with bituminous binder VG-40 @4.5% by weight of total mix and filler, transporting the hot mix to work site, laying with hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve to desired compaction as per MORTH Specification CLAUSE No 505 complete in all respects (Morth/5.04/505(B)) |
| 10 | 60/50mm compacted thickness with bitumen perpetration of [email protected]% by weight of total mix. (MORTH-/5.05/505(B)) |
| 11 | Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG-40 @ 5.00 per cent of mix and filler, transporating the hot mix to works site ,laying with sensor control to the required greade,level and vibratory rolling with smooth, wheeled,vibratory and tandom rollers to achieve the desired compaction as per MORTH specification clause 509 complete in all respects. MORTH-509/AR/GNIDA (Grade-II) 40mm Thick |
| 12 | Cement concrete with 4cm gaugeApproved stone ballast coarse sand & cement in the proportion of 8:4:1 including supply of all materials labour tools & Plants etc required for proper completion of the work |
| 13 | 8:4:1 (1 Cement 4: Coarse sand :8 graded stone aggregate 40mm nominal size) (SOR-20/281/5.08) |
| 14 | Plain/Reinforced Cement concrete in open foundation complete as per Drawing and Technical Specifications. (MORTH-20/9.06/E/Case-II) |
| 15 | RCC Grade M-25 using batching plant transit mixture and manual placing (MORTH-20/9.06/E/Case-II) |
| 16 | Steel reinforcement for RCC work including straightening cutting bending placing in position and binding all complete upto plinth level |
| 17 | Thermo Mechanically treated bars of grade Fe-500D or more. (SAIL Steel) (DSR-18/5.22.6/AR) |
| 18 | Cartage of earth or fly ash when added to schedule item no. 253 : 5Km. and beyond (SOR-20/261(C)) |
| 19 | Labour cess and GST will be paid extra as per Govt. orders. Please Enable Macros to View BoQ information |