| 1 | Earth work excavation for foundation by manual means for Isolated, Combined and Other type foundations in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and initial lift of 2.00mts. and clearing and levelling the site, etc., complete complying with standard specification and as directed by the departmental officers. |
| 2 | Earth work open excavation by manual means in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the excavated earth with a lead of 10 mts. within the compound in places shown by the departmental officers and clearing and levelling the site, etc., complete complying with standard specification and as direct-ed by the departmental officers. |
| 3 | Supplying and filling in foundation and basement with Well Gravel in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 4 | Plain Cement Concrete 1:5:10 (one cement, five fine aggregates and ten coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 5 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation - Plinth Beam |
| 6 | Supplying and erecting steel centering including necessary supports For plane surfaces such as rectangular or square RCC columns etc. which require only nominal strutting using mild steel sheets made of 10 gauge thick welded with MS angle size 40mm x 40mm x 5 mm and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick).etc..complete in all floors complying with standard specifcation. Steel Adjustable telescopic props shall be rovided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid). |
| 7 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requirements of IS standards. (No separate payment will be made by the Department for the excess usage of materials) - Upto Basement |
| 8 | up to basement |
| 9 | ground floor |
| 10 | Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors. |
| 11 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9\\" X 43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 12 | Supply and fixing of M.S Grills with Doors and Windows with one coat of Red oxide with Primer including all costs such as welding, grinding and fabrication charges, cost and conveyance of all materials to site etc,complete as per standard specification. |
| 13 | Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications |
| 14 | Special ceiling plastering and finishing the exposed surface of all RCC items of work such as slabs, beams, sunshades, facia, canopy slab, staircase waist slab, landing slab etc., with Cement Mortar 1:3 (One Cement and Three Plastering Sand) 10mm thick including mortar plasticizer at 200ml per 50Kg of cement used , hacking the surfaces and curing, etc., in all floors complying with standard specification and as directed by the departmental officers |
| 15 | Painting two coats for Exterior surface with approved Exterior Plastic Emulsion paint approved quality and colour over a priming coat, including thorough scrapping, clean removal of dirt, etc complete and including necessary plaster of paris, putty, wherever required etc, complete as per standard specification. |
| 16 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete complying with standard specification and as directed by the departmental officers. (The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) Please Enable Macros to View BoQ information |