| 1 | Dismantling of defective capacitor units from the APFC panel after suitably discharging the left-over charge on capacitors to ensure safety of the working persons along with dismantling of capacitors, APFC relay, indications lights, meters, A/M switches, MCCBs including dismantling of terminations and existing hardware and rusted parts and various other items requiring change in the panel as required at site. |
| 2 | Replacement of defective Super Heavy Capacitor units of various capacities with new capacitors units, rated at 440V, 3 Phase, 50 Hz system complete with terminal cover, cable end entry, mounting structure and hardware etc. – Make Standard |
| 3 | Banking of capacitors of various capacities with multistrand copper wires & lugs/ Aluminium bus bars and mounting arrangement for parallel connection to form suitable rating capacitor bank. |
| 4 | Power wiring with 10 sq. mm multistrand copper wires for connection between capacitors and bus bar using copper lugs and necessary hardware etc. as required at site. |
| 5 | Replacement of defective capacitor duty contactors suitable for 25 KVAR capacitor with new capacitor duty contactor. Make- Standard/EPCOS |
| 6 | Replacement of defective triple pole MCB of 63 A capacity with new MCB for operation and safety of individual capacitor bank – Make L&T/EPCOS/Standard |
| 7 | Replacement of defective triple pole MCB of 32A capacity with new MCB for operation and safety of individual capacitor bank - Make L&T/EPCOS/Standard |
| 8 | Replacement of defective APFC relay, with new microprocessor based APFC relay having digital display of power factor and other parameters to sense power factor through control CT and give phased impulses to contactor coils for switching ON-OFF required number of capacitors as per requirement to achieve target power factor. Make- Standard |
| 9 | Programming of APFC relay for target power factor including setting of various parameters and keeping updated indications of the efficiency of electrical power usage, and improving it for reducing the power losses and avoid penalties from utility companies. |
| 10 | Replacement of defective/ burnt out LED indication lights of various colours with new indication lights, Make- Standard/ L&T |
| 11 | Installation of all above components in the existing capacitor banks with suitable fabrication work to accommodate new items in the existing enclosure/ structure for alignment of components and ease of termination, complete with hardware on the mounting structure and termination of existing cables with lugs, tapes etc. complete with earthing of the capacitor banks, touching the rusted parts of the panel structure with paint for protection from moisture etc. as required at site. |
| 12 | Servicing of APFC panels including complete dusting of the panel, cleaning of contact points, decarbonizing of Joints, alignment of doors, checking of all nuts & bolts, control circuit and power circuit wiring dressing and renovation of control and power terminations etc. as required at site. |
| 13 | Testing and commissioning of complete APFC Panel installation including following:1. Meggering of complete capacitor installation using 500V megger2. Continuity test for checking continuity of all circuits to ensure that all circuits are properly wired.3. Checking function and efficiency of various components of APFC panel. |
| 14 | Repair of static capacitor of TransformerChecking of capacitors and dismantling of defective capacitors from static capacitorsbanks including dismantling of terminations, wirings, hardware, as required at site. |
| 15 | Supply of super heavy-duty capacitors of various capacities rated at 440V, 50HZ, 3 phase AC complete with terminal cover and discharge device for replacement of defective capacitors of static capacitor banks- Make Standard |
| 16 | Banking of capacitors of various capacities with multistrand copper wires & lugs/ aluminium bus bars and mounting arrangement for parallel connection to form suitable rating capacitor bank. |
| 17 | Installation & connection of capacitors as described above using necessary hardware, mounting arrangement and termination with multistrand copper wires, lugs, tapes etc. as required at site. |
| 18 | Old Scrap Rebate Please Enable Macros to View BoQ information |