| 1 | Credit of old bricks and Brick Bats |
| 2 | Supply, carriage and fixing of R.C.C lids Dia 21` |
| 3 | Supply, carriage and fixing of R.C.C panels of requisite size as per approved design drawing and P.W.D. Specifications (27` x 27`) thickness in 0.25` of C.C. 1:3:6 with requested reinforcments as per the discharge of UGPL as per appoved desgin and P.W.D. Specifications completed in all respect to the satisfaction to the Engineer in charge |
| 4 | Providing and fixing of C.I. Nakkas |
| 5 | Civil Work |
| 6 | [11.4.2]10 mm thick cement plaster 2. 1:3 (1 cement: 3 fine sand) [Through Rate] |
| 7 | [20.62.5]Providing, lowering, laying, cutting (cut surface to be uniformly finished), jointing with rubber rings marked with IS : 5382 and testing of SPIGOT AND SOCKETTED RCC, NP2 MARKED WITH IS : 458-1988 and specials into trenches for all depths including carriage, loading, unloading, stacking, handling, re-handling etc. complete is all respects to the satisfaction to the Engineer - in -charge. 5. 400 mm i/d [Through Rate] |
| 8 | [21.28]Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, re-handling etc., complete in all respect to the satisfaction of Engineer-in-charge [Through Rate] |
| 9 | [21.95.3]Providing lowering cutting jointing and testing RCC pipe class NP3 as per IS-458-2003 with spigot and socketed joints manufactured with ISI marked sulphate resistance cement as per ISI 12330 with rubber rings ISI marked antiternmite as required at site in to trenches for all depths and laying out the same to correct alignment gradients and levels including dressing and trimming and cutting of concrete beds and side of trenches, if required jointing with rubber rings in trenches and jointing with 1:3/2 cement sand mortar and with end dowels filled with 1:3/2 cement sand mortar and finishing the joints at an angle of 45 degree with faces of spigot of socket joints cutting and finishing the cut surface to a uniform finish etc. as fully described in item No. 21.38, item 21.44, item 21.45, and item 21.46 including cartage loading and unloading complete in all respects. the internal diametric of the sewer being: 3. 450 mm [Through Rate] |
| 10 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 11 | [4.16.1.3]Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.3. All kind of soil Pipes, cables etc, exceeding 300 mm dia but not exceeding 600 mm dia. [Through Rate] |
| 12 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] |
| 13 | [5.7.4]Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. 4. In cement mortar [Through Rate] |
| 14 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 15 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 16 | [7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |