| 1 | PART A :-Construction of 0.28 CKM 33KV O/H line using 13 Mtr. WPB Pole & 100 Sq.mm. AAA Conductor33 KV Cut Point with 90 Degree AngleWPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 2 | Straight Cross Arm Channel(GI) 100 x 50 x 6 mm, 9.56 KG/mtr, each Channel(GI) length 1.7 Mtr., 4 No's of Channel(GI) = (4x 9.56x1.7) |
| 3 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 4 | Straight Cross Arm Top Channel(GI) 100 x 50 x 6 mm, 9.56 KG/mtr, each Channel(GI) length 0.306 Mtr., 4 No's of Channel(GI) = (4x 9.56x0.306) |
| 5 | Danger Plate, 1 no's. |
| 6 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 7 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 8 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 9 | 33KV pin insulator polymer (4 No's each 90 Deg. Cut point) |
| 10 | H W fitting(B&S)90KN,4 Bolt |
| 11 | Disc insulator (B&S)90 KN polymer |
| 12 | Earthing of Support ( Coil Type ) |
| 13 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 14 | Wedge connector for 100 sq.mm AAA conductor |
| 15 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 16 | H.T. Stay set (Complete ) |
| 17 | H.T. Stay Insulator Type-C (2 No's.) |
| 18 | 7/8 SWG Stay Wire 15kg /stay |
| 19 | GI Nut , Bolt & Washer of different sizes (11.31 Kg each 90 deg. Cut point) |
| 20 | POLYCARBONATE BIRD GUARD |
| 21 | Black Paint(GIS Numbering & Zebra Stripping) |
| 22 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 23 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 24 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 25 | Fixing of complete 33KV line Complete stay set includes1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard.Note:- Excavation of earth will be done of size 500X500X1500 mm. |
| 26 | 33 KV Pin PointsWPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 27 | 33 KV V cross Arm (GI) 22Kg each |
| 28 | Top bracket 100x50x6mm GI Channel(GI) ( 2kg each) |
| 29 | Danger Plate, 1 no's. |
| 30 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 31 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 32 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 33 | 33KV pin insulator polymer |
| 34 | Earthing of Support ( Coil Type ) |
| 35 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 36 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 37 | 100 sq.mm AAA conductor |
| 38 | POLYCARBONATE BIRD GUARD |
| 39 | Black Paint(GIS Numbering & Zebra Stripping) |
| 40 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 41 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 42 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 43 | PART B :-Construction of 0.12 CKM 33 KV O/H line using 14 Mtr. H Pole & 100 Sq.mm. AAA Conductor33 KV Cut Point with 90 Degree Angle14 Mtr. Long H-Pole(GI) (Total weight with Base Plate & Stiffner= 782.67 KG) |
| 44 | Straight Cross Arm Channel(GI) 100 x 50 x 6 mm, 9.56 KG/mtr, each Channel(GI) length 1.7 Mtr., 4 No's of Channel(GI) = (4x 9.56x1.7) |
| 45 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 46 | Straight Cross Arm Top Channel(GI) 100 x 50 x 6 mm, 9.56 KG/mtr, each Channel(GI) length 0.306 Mtr., 4 No's of Channel(GI) = (4x 9.56x0.306) |
| 47 | Danger Plate, 1 no's. |
| 48 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 49 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 50 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 51 | 33KV pin insulator polymer (4 No's each 90 Deg. Cut point) |
| 52 | H W fitting(B&S)90KN,4 Bolt |
| 53 | Disc insulator (B&S)90 KN polymer |
| 54 | Earthing of Support ( Coil Type ) |
| 55 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 56 | Wedge connector for 100 sq.mm AAA conductor |
| 57 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 58 | H.T. Stay set (Complete ) |
| 59 | H.T. Stay Insulator Type-C (2 No's.) |
| 60 | 7/8 SWG Stay Wire 15kg /stay |
| 61 | GI Nut , Bolt & Washer of different sizes (11.31 Kg each 90 deg. Cut point) |
| 62 | POLYCARBONATE BIRD GUARD |
| 63 | Black Paint(GIS Numbering & Zebra Stripping) |
| 64 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 65 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2300mm) = 0.58Cu.mtr(Per Pole) |
| 66 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 67 | Fixing of complete 33KV line Complete stay set includes1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard.Note:- Excavation of earth will be done of size 500X500X1500 mm. |
| 68 | 33 KV Pin Points14 Mtr. Long H-Pole(GI) (Total weight with Base Plate & Stiffner= 782.67 KG) |
| 69 | 33 KV V cross Arm (GI) 22Kg each |
| 70 | Top bracket 100x50x6mm GI Channel(GI) ( 2kg each) |
| 71 | Danger Plate, 1 no's. |
| 72 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 73 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 74 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 75 | 33KV pin insulator polymer |
| 76 | Earthing of Support ( Coil Type ) |
| 77 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 78 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 79 | 100 sq.mm AAA conductor |
| 80 | POLYCARBONATE BIRD GUARD |
| 81 | Black Paint(GIS Numbering & Zebra Stripping) |
| 82 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 83 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2300mm) = 0.58Cu.mtr(Per Pole) |
| 84 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 85 | PART C: Installation of 01 No of existing 33/0.433 KV, 250 KVA DTR on Proposed DP (existing DTR will be used)WPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 86 | 9 Mtr. long 300 Kg. PSC Pole |
| 87 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 88 | EYE hook for XLPE Aerial bunched Cable |
| 89 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 90 | LT Cable raising Channel(GI) 75x40x4.8 mm GI Channel(GI) (1000 mm long)(7.14Kg./Mtr., 6 No's.) (Each 6x1.000x7.14= 42.84 Kg) |
| 91 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 92 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 93 | Isolation support Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 4.3 Mtr., 2 no's Channel(GI) required =( 7.14x4.3x2) |
| 94 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 95 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 96 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 97 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 98 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 2 nos Angle(GI) required = (4.5x3.512x2) |
| 99 | Isolator Operating Down Pipe Support Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 1x7.14x0.8) |
| 100 | Down Pipe Diagonal Support Angle(GI), 4.5Kg./mtr., each Angle(GI) length 0.388mtr., 1 nos Angle(GI) required = (1*4.5*0.388) |
| 101 | Down Pipe Base Support Angle(GI), 4.5Kg./mtr., each Angle(GI) length 0.34mtr., 1 nos Angle(GI) required = (1*4.5*0.340) |
| 102 | Isolator Support Side Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.5 mtr., 2 no's Channel(GI) required =( 2x9.56x0.5) |
| 103 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 104 | LT Distribution Box with MCCB, Aluminium Busbar for 3 Bay with kit kat fuse for 250 KVA S/S |
| 105 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 106 | 1 Cx 630 mm2 LT XLPE Cable(Un-Armoured) |
| 107 | LT Cable Supporting Channel(GI) 100 X 50 X 6 MM GI Channel(GI) (2000 mm long)(9.56 Kg./Mtr., 2 No's.) (Each 2x2x9.56= 28.56 Kg) |
| 108 | LT Cable Supproting Angle(GI), 50x50x6mm.GI 4.5Kg./mtr., each Angle(GI) length 2 mtr., 4 nos Angle(GI) required = (4.5x4x2) |
| 109 | Supply of 1.1kV, 4Core, 150 sqmm, XLPE insulation armoured -Aluminium UG cable from LTDB to Pole |
| 110 | 33 KV 1250 AMP Double break (Turn & twist center rotating) isolator without earth switch with Pl(Polymer) |
| 111 | Expulsion fuse cut out 33 KV 200Amp |
| 112 | Expulsion fuse link 33 KV 10Amp |
| 113 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 114 | POLYCARBONATE BIRD GUARD |
| 115 | Disc insulator (B&S)90 KN polymer |
| 116 | H W fitting (B&S)90KN(4bolted) |
| 117 | Lightning Arrester(30KV,10KA) Station Class 2 |
| 118 | 33KV pin insulator polymer |
| 119 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 120 | HT stay set complete |
| 121 | HT stay insulator TYPE-C |
| 122 | 7/8 SWG stay wire,(15Kg./ Set) |
| 123 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 124 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 125 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 126 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 127 | Danger plate 11kv |
| 128 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 129 | Name plate |
| 130 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 131 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 132 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 133 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 134 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (3.5X2.5X0.1)= 0.875 Cu. mtr. |
| 135 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 136 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earthresistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 137 | LTDB Plinth |
| 138 | DTR Plinth |
| 139 | Laying of 4 Cx 150 mm2 LT XLPE Cable |
| 140 | Laying of 1.1kV cable from 400 to 1000sqmm |
| 141 | SITC and Erection of GI Fencing with Gate |
| 142 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) (For PSC Pole) |
| 143 | Supply of AL Lugs suitable for 400 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 144 | Supply of AL Lugs suitable for 150 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 145 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 1C 300-1000 sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 146 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 120-185sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 147 | PART D -Shifting & Re-Construction of LT AB Cable Line Length with 33 Mtr. Span using -4Cx95 mm2 (P)+1Cx95 mm2(M)+1CX16 mm2(Street Light) on existing pole -0.260 KmLT Stay set Complete |
| 148 | 7/12 SWG GI stay wire, Grade -2 |
| 149 | LT stay Clamp ( 1.40Kg/pair) |
| 150 | LT Stay insulator |
| 151 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 152 | EYE hook for XLPE Aerial bunched Cable |
| 153 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 154 | Suspension Clamp with EYE hook for ABC |
| 155 | 4C×95 mm² (P)+1C×95 mm²(M)+1CX16 mm²(Street Light) (LT AB Cable) |
| 156 | 4 WAY SERVICE Distb. Box with kit kat fuse and Aluminium bus bar. |
| 157 | Insulated piercing connector.Type-A-main 50 to 150 sq.mm & Tap-50 to 150 sq.mm |
| 158 | Insulated piercing connector.Type-C-main 16 to 95 sq.mm & Tap-1.5 to 16 sq.mm |
| 159 | Fixing of LT Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.) |
| 160 | PART E -Construction of Line Protecting Guarding on Single Pole to single pole having span 30 MtrGuarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 2.2 mtr., 4 no's Channel(GI) required =( 4x7.14x2.2) ( For Single Pole) |
| 161 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 162 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 163 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 164 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 165 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 166 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 167 | PART F -Construction of Line Protecting Guarding on Double Pole to Single-Pole for Road Crossing having span 30 Mtr.Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 3.5 mtr., 4 no's Channel(GI) required =( 4x7.14x3.5) ( For Double Pole) |
| 168 | Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 2.2 mtr., 4 no's Channel(GI) required =( 4x7.14x2.2) ( For Single Pole) |
| 169 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 170 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 171 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 172 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 173 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 174 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 175 | PART G-Dismantling Portion. Dismantling of 11/13 Mtr. Joist/WPB Pole- 150X150 mm/ 160X160 mm |
| 176 | Dismantling of 9/8 Mtr. PCC/Joist Pole |
| 177 | Dismantling / Removal of V Cross arm from pole |
| 178 | Dismantling of 11kV Pin Insulator with Pin |
| 179 | Dismantling / Removal of MS Channel. from Double Pole Structure /pole |
| 180 | Dismantling of existing 11/0.4kV, 33/0.4KV, 250kVA Three Phase Distribution Transformer including removal of HT/LT leads, earth connections and unloading by crane if required. |
| 181 | Dismantling of ACSR/AAAC 34/ 55mm2 from overhead line |
| 182 | Dismantling of ACSR/AAAC 80/100 mm2 from overhead line, |
| 183 | Dismantling of varous size of LT AB Cable |
| 184 | Dismantling of 11 kV /33KV GO/AB Switch/Isolator/DD fuse/fuse set |
| 185 | Dismantling of 33KV V cross arm |
| 186 | Dismantling of 33KV Pin Insulator with F Bracket |
| 187 | Dismantling of 33KV Disc Insulator with Hardware |
| 188 | Dismantling of all accesseries(Disc,pin insulator, v cross arm, danger board, steel structure of cut point from Double pole structure at 9/10/11/13 Mtr Please Enable Macros to View BoQ information |