| 1 | Cutting uprooting and clearing jungles including shrubs, water weeds,bushes, trees, plants, upto 30 cm girth including removing as directed by Engineer-in-charge. |
| 2 | Earthwork in excavation in the canals / drainage channels / borrow pits / River bed / slope of bank as noted below as per designed section & throwing the spoils in layers of 25 cm. for making banks as per profile or to deposit the same in any other place within an initial lead of 30 metre and initial lift of 1.5 metre including breaking clods, rough dressing etc. complete as per direction of the Engineer-in-charge.a) Ordinary soil / Local soil/ soil mixed with moorum or kankar/ silt, dry or moist, slushy silt/ sticky soil. |
| 3 | Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engineer-in-charge. |
| 4 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. |
| 5 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling with approved material complete as per direction of the Engineer-in-Charge. I. In all sorts of soil excluding marshy soil & rocks ( soft 0r hard ) by mnual means.a) upto 3 m depth.(iv) Without pumping out water and shoring. |
| 6 | Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steelsheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as per specification and direction.(b) Where staging is not required. |
| 7 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation and upto roof of ground floor/upto 4 m (i) Tor steel/Mild Steel I. SAIL/ TATA/RINL |
| 8 | “Cast-in-situ cement concrete blocks or lining units as per designed section and specification, in normal mix propotion 1:1.5:3 (corrsponding to M20 grade with well graded 20 mm down stone metal aggregate, laid in position by casting in alternative panels or otherwise to keep a gap of 12mm between the adjacent units, over a layer of polythene sheet of thickness not less than 100 to act as aseperator between the bottom surface of the block and the sand cushion/filter material laid below the blocks ,including dressing , ramming, shuttering, finishing the exposed surface by trowel without adding any additional cement and sand mortar ,curing and filling the gaps between the adjacent units by 5.6mm down coarse aggregate to be compacted properly, with all leads and lifts including supply and carriage of all materials, complete, without the cost of sand cushion/filter.(The rate is exclusive of the cost of stone aggregate and its carriage upto site. Construction wing has to add the cost of same from the SoR of PW (Roads) to derive the consolidated rate. Consumption chart of the USoR may be used for assessing the quantity of coarse aggregates per cum of concrete).(Stone Aggregate of Pakur or Rajmahal,or broken stone of North Bengal varieties)Note:provisions of the latest departmental manual for lining in Irrigation Canals are to be followed ,when ever applicable. Please Enable Macros to View BoQ information |