| 1 | Earthwork inexcavationof foundation trenches or drains, inall sorts of soil (includingmixed soil but excluding lateriteor sandstone) including removing, ead of 75m. as directed. The item includes necessary trimming the sides of renches, levelling,dressing and ramming the bottom, bailing out water as required complete. |
| 2 | Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) |
| 3 | Brick soling with picked jhama bricks including preparation of bed as necessary with brick joints properly filled in and packed with powdered earth and including necessary cushion of similar material below the soling (and in between layers when more than one layer is used) completes as per direction with new brick. |
| 4 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. |
| 5 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur Variety |
| 6 | First class Brick work in cement sand mortar in steining of well, pier, abutment, wing wall, parapets cross drain. H.P. culverts, guard wall etc. including curing, scaffolding, raking out joints etc. complete including cost and carriage of all materials. Brick masonry in 1:4 cement mortar |
| 7 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur Variety |
| 8 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (i) Tor steel/Mild Steel I. Other than SAIL/TATA/RINL. |
| 9 | Hire and labour charges for shuttering with centering and necesserry staging and using approved stautprops , planks approved thickness with required bracing incuilding fitting,fixing and striking out after completion of work |
| 10 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] With 1:4 cement mortar. 20 mm thick plaster, in ground floor |
| 11 | Neat cement punning about 1.5 mm. thick in wall, dado, window, sills, floor, drain etc.NOTE : Cement 0.152 cu.m. per 100 sq.m. |
| 12 | Fixing or Erection of Falak at Working Site. |
| 13 | TOTAL WITHOUT GST AND LABOUR CESS |
| 14 | Including GST @ 18% |
| 15 | Including Cess @ 1% Please Enable Macros to View BoQ information |