| 1 | New installation of 2x200KW, 1200mm belt conveyor with 930 mtr structure in 33 x cut in RV seam for LHCM . (Inclusive of EPF/CMPF) |
| 2 | Loading, unloading, carrying, transportation of 2x200 KW, 1200mm heavy duty drive head with Motor and starter from surface to mentioned belt conveyor - |
| 3 | Loading, unloading, carrying, transportation of other structure assoiciated with Drive head including discharge unit, loop take assembly, tail end assembly and safety guard from surface to mentioned belt conveyor - |
| 4 | Loading, unloading, carrying, transportation of 930 mtr structure at mentioned belt conveyor -@ 150.67kg per mtr |
| 5 | Loading, unloading, carrying, transportation of belt from surface to belt install site then laying and lapping of belt |
| 6 | Loading, unloading, carrying, transportation of 01 nos of load table from surface to mentioned belt conveyor -1MT |
| 7 | Faencing of drive tail end etc including cost of DA,oxygen and welding electrodes |
| 8 | Fabrication of load table at surface workshop including cost of DA, Oxygen & welding elctrodes. |
| 9 | Fabrication and fitting of dischage and tail end scrapper |
| 10 | Loading, unloading transportation of control cable & assy laying and fitting |
| 11 | Fabrication & fitting of veticle support for structure hanging portion from discharge to loop take up including coast of DA and 02 nos oxygen cylibnder |
| 12 | Transportation and placing electrical VCB , cable (power and control) from surface to drive head - 1 set |
| 13 | Holding down bolt for drive head |
| 14 | Tail end shifting |
| 15 | New installation of 2x150KW, 1200mm belt conveyor with 325 mtr structure in 8Dip first belt at RV seam for LHCM . (Inclusive of EPF/CMPF) |
| 16 | Loading, unloading, carrying, transportation of 2x150 KW, 1200mm heavy duty drive head with Motor and starter from surface to mentioned belt conveyor - |
| 17 | Loading, unloading, carrying, transportation of other structure assoiciated with Drive head including discharge unit, loop take assembly, tail end assembly and safety guard from surface to mentioned belt conveyor - |
| 18 | Loading, unloading, carrying, transportation of 325 mtr structure at mentioned belt conveyor -@ 146kg per mtr |
| 19 | Loading, unloading, carrying, transportation of belt from surface to belt install site then laying and lapping of belt |
| 20 | Loading, unloading, carrying, transportation of 01 nos of load table from surface to mentioned belt conveyor -1MT |
| 21 | Faencing of drive tail end etc including cost of DA,oxygen and welding electrodes |
| 22 | Fabrication of load table at surface workshop including cost of DA, Oxygen & welding elctrodes. |
| 23 | Fabrication and fitting of dischage and tail end scrapper |
| 24 | Loading, unloading transportation of control cable & assy laying and fitting |
| 25 | Fabrication & fitting of veticle support for structure hanging portion from discharge to loop take up including coast of DA and 02 nos oxygen cylibnder |
| 26 | Transportation and placing electrical VCB , cable (power and control) from surface to drive head - 1 set |
| 27 | Holding down bolt for drive head |
| 28 | tail end shifting |
| 29 | New installation of2x110KW, 225mtr, 1000mm belt conveyor in 8dip 3rd belt for LHCM In RV seam. (Inclusive of EPF/CMPF) |
| 30 | Loading, unloading, carrying, transportation of discharge unit with required girders from surface to mentioned belt conveyor -3MT |
| 31 | Loading, unloading, carrying, transportation of heavy duty drive head from surface to mentioned belt conveyor -10.5MT |
| 32 | Loading, unloading, carrying, transportation of tail end assuy along with V scapper tail end guard decking plate from surface to mentioned belt conveyor -1MT |
| 33 | Loading, unloading, carrying, transportation of 225 mtr structure at mentioned belt conveyor -@ 110 kg per mtr |
| 34 | Loading, unloading, carrying, transportation of belt from surface to belt install site then laying and lapping of belt |
| 35 | Loading, unloading, carrying, transportation of loop take up from surface to mentioned belt conveyor -4.75MT |
| 36 | Loading, unloading, carrying, transportation of 01 nos of load table from surface to mentioned belt conveyor -1MT |
| 37 | Fencing of drive tail end etc including cost of DA,oxygen and welding electrodes |
| 38 | Fabrication of load table at surface workshop including cost of DA, Oxygen & welding elctrodes. |
| 39 | Fabrication and fitting of dischage and tail end scrapper |
| 40 | Loading, unloading transportation of control cable & assy laying and fitting |
| 41 | Transportation and placing electrical VCB, starter, cable (power and control) from surface to drive head - 1 set |
| 42 | Holding down bolt for drive head |
| 43 | New installation of 2x150KW, 1200mm belt conveyor with 215 mtr structure at RV seam in 8 dip 2nd belt. (Inclusive of EPF/CMPF) |
| 44 | Loading, unloading, carrying, transportation of 2x150 KW, 1200mm heavy duty drive head with Motor and starter from surface to mentioned belt conveyor - |
| 45 | Loading, unloading, carrying, transportation of other structure assoiciated with Drive head including discharge unit, loop take assembly, tail end assembly and safety guard from surface to mentioned belt conveyor - |
| 46 | Loading, unloading, carrying, transportation of 215mtr structure at mentioned belt conveyor -@ 146kg per mtr |
| 47 | Loading, unloading, carrying, transportation of belt from surface to belt install site then laying and lapping of belt 360mtr |
| 48 | Loading, unloading, carrying, transportation of 01 nos of load table from surface to mentioned belt conveyor -1MT |
| 49 | Faencing of drive tail end etc including cost of DA,oxygen and welding electrodes |
| 50 | Fabrication of load table at surface workshop including cost of DA, Oxygen & welding elctrodes. |
| 51 | Fabrication and fitting of dischage and tail end scrapper |
| 52 | Loading, unloading transportation of control cable & assy laying and fitting |
| 53 | Fabrication & fitting of veticle support for structure hanging portion from discharge to loop take up including coast of DA and 02 nos oxygen cylibnder |
| 54 | Transportation and placing electrical VCB , cable (power and control) from surface to drive head - 1 set |
| 55 | Holding down bolt for drive head |
| 56 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |